3856 N BERRY DR 91604
Certificate Information: 3856 N BERRY DR 91604
- Application / Permit
- 21030-10000-05417
- Plan Check / Job No.
- B21LA11628
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR SITE AND BACKFILL FOR (N) RETAINING WALL
- Permit Issued
- Issued on 2/9/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/19/2022
Permit Application Status History
| Submitted | 6/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2021 | JESSE JIMENEZ |
| Corrections Issued | 6/29/2021 | JESSE JIMENEZ |
| Building Plans Picked Up | 6/30/2021 | APPLICANT |
| Applicant returned to address corrections | 7/25/2021 | ZAW HAN |
| Applicant returned to address corrections | 8/11/2021 | FERNANDO FLORES |
| Plan Check Approved | 8/13/2021 | FERNANDO FLORES |
| Issued | 2/9/2022 | APPLICANT |
| Permit Finaled | 10/19/2022 | MANUEL TEJADA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | D K R Construction Inc; Lic. No.: 1070450-B | 7110 FOREST HILLS RD WEST HILLS, CA 91307 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 3/22/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Initial Grading | 3/22/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Drainage Devices/Catch Basin | 6/6/2022 | Partial Inspection | MANUEL TEJADA |
| Sub-Drain | 6/6/2022 | Partial Approval | MANUEL TEJADA |
| Bottom/Toe | 10/18/2022 | Approved | MANUEL TEJADA |
| Final | 10/18/2022 | Not Ready for Inspection | MANUEL TEJADA |
| Rough | 10/18/2022 | Approved | MANUEL TEJADA |
| Final | 10/19/2022 | Permit Finaled | MANUEL TEJADA |