4702 N FIGUEROA ST 90042
Certificate Information: 4702 N FIGUEROA ST 90042
- Application / Permit
- 21030-10000-04854
- Plan Check / Job No.
- B20LA08587
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- EXCAVATION AND BACKFILL FOR THE INSTALLATIONS OF STORM DRAIN AND SEWER STRUCTURES. LABOE-LA SANITATION PROJECT.
- Permit Issued
- Issued on 8/4/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/19/2023
Permit Application Status History
| Submitted | 5/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2020 | JOHNNY WU |
| Corrections Issued | 6/16/2020 | JOHNNY WU |
| Quality Review Completed | 6/23/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 7/9/2020 | APPLICANT |
| Applicant returned to address corrections | 7/20/2020 | JOHNNY WU |
| Applicant returned to address corrections | 10/29/2020 | JOHNNY WU |
| Applicant returned to address corrections | 8/2/2021 | JOHNNY WU |
| Plan Check Approved | 8/3/2021 | JOHNNY WU |
| Issued | 8/4/2021 | APPLICANT |
| Permit Finaled | 4/19/2023 | ROBERT HUGHES |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 7/22/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 8/2/2021 | JOHNNY WU |
Contact Information
| Contractor | Prlich Mike & Sons Inc; Lic. No.: 760474-A | 5103 ELTON ST BALDWIN PARK, CA 91706 |
| Engineer | Amante,, Carlos Vergara; Lic. No.: GE2724 | 108 3176 PULLMAN ST COSTA MESA, CA 92626 |
| Engineer | Mote,, Christopher Stephen; Lic. No.: C87384 | 2415 MOHAWK ST 107 PASADENA, CA 91107 |
| Geologist | Schluter,, Mark Brian; Lic. No.: EG1415 | 142 MADELINE DRIVE MONROVIA, CA 91016 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/22/2021 | Approved | ROBERT HUGHES |
| Bottom/Toe | 9/23/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Rough | 9/30/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Bottom/Toe | 1/13/2022 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 2/11/2022 | Partial Approval | ROBERT HUGHES |
| Excavation | 2/11/2022 | Partial Approval | ROBERT HUGHES |
| Fill/Backfill | 2/14/2022 | Partial Approval | ROBERT HUGHES |
| Fill/Backfill | 2/15/2022 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 2/17/2022 | Partial Approval | LANNY MERRICK |
| Initial Grading | 3/3/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Rough | 3/21/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Fill/Backfill | 4/19/2022 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 4/19/2023 | Approved | ROBERT HUGHES |
| Final | 4/19/2023 | Permit Finaled | ROBERT HUGHES |
| Rough | 4/19/2023 | Approved | ROBERT HUGHES |