4516 N MARIOTA AVE 91602
Certificate Information: 4516 N MARIOTA AVE 91602
- Application / Permit
- 21030-10000-04666
- Plan Check / Job No.
- B21LA13256
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading for Remove and recompaction. 1 OF 2
- Permit Issued
- Issued on 1/12/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/12/2026
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | VU NGUYEN |
| Corrections Issued | 8/24/2021 | VU NGUYEN |
| Quality Review Completed | 8/30/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 9/2/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 12/20/2021 | APPLICANT |
| Plan Check Approved | 1/12/2023 | KEVIN MORALES |
| Issued | 1/12/2023 | APPLICANT |
| Permit Finaled | 1/12/2026 | ALEXANDER HELFER |
Permit Application Clearance Information
| "D" conditions | Cleared | 12/8/2021 | JASON CHAN |
| CPC | Cleared | 12/8/2021 | JASON CHAN |
| CPC | Cleared | 12/8/2021 | JASON CHAN |
| CPC | Cleared | 12/8/2021 | JASON CHAN |
| CPC | Cleared | 12/8/2021 | JASON CHAN |
| CPC | Cleared | 12/8/2021 | JASON CHAN |
| Miscellaneous | Cleared | 12/8/2021 | JASON CHAN |
| Miscellaneous | Cleared | 12/8/2021 | JASON CHAN |
| ZA Case | Cleared | 12/8/2021 | JASON CHAN |
| Low Impact Development | Cleared | 1/9/2022 | MARTIN FRAGOSO |
Contact Information
| Contractor | A R C.City; Lic. No.: 1050930-B | P O BOX 13152 LOS ANGELES, CA 90013 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/3/2024 | Partial Inspection | MANUEL TEJADA |
| Initial Grading | 6/30/2025 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 7/14/2025 | Corrections Issued | ALEXANDER HELFER |
| Rough | 7/18/2025 | Corrections Issued | ALEXANDER HELFER |
| Approved Compaction Report | 7/29/2025 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 9/9/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Bottom/Toe | 9/10/2025 | Partial Approval | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 9/25/2025 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 9/29/2025 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 9/30/2025 | Partial Inspection | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 10/2/2025 | Corrections Issued | ALEXANDER HELFER |
| Final | 12/15/2025 | Not Ready for Inspection | MANUEL TEJADA |
| Rough | 12/15/2025 | Not Ready for Inspection | MANUEL TEJADA |
| Approved Compaction Report | 12/17/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Bottom/Toe | 12/19/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Final | 12/19/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Rough | 12/19/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Bottom/Toe | 12/29/2025 | Not Ready for Inspection | MANUEL TEJADA |
| Final | 12/29/2025 | Partial Inspection | MANUEL TEJADA |
| Rough | 12/29/2025 | Not Ready for Inspection | MANUEL TEJADA |
| Bottom/Toe | 1/9/2026 | Approved | ALEXANDER HELFER |
| Final | 1/9/2026 | Partial Inspection | ALEXANDER HELFER |
| Rough | 1/9/2026 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 1/12/2026 | Approved | ALEXANDER HELFER |
| Final | 1/12/2026 | Permit Finaled | ALEXANDER HELFER |