5235-5237 W JEFFERSON BLVD 90016
Certificate Information: 5235-5237 W JEFFERSON BLVD 90016
- Application / Permit
- 21030-10000-04559
- Plan Check / Job No.
- B21LA12955
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING - EXCAVATE AND BACKFILL FOR BASEMENT WALLS AND SITE GRADING WORK. 3 OF 3
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/27/2023
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Green Plans Picked Up | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | SAM CHANG |
| Corrections Issued | 8/16/2021 | SAM CHANG |
| Quality Review Completed | 8/20/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Applicant returned to address corrections | 10/28/2021 | SAM CHANG |
| Applicant returned to address corrections | 11/10/2021 | SAM CHANG |
| Disabled Access Plans Picked Up | 3/25/2022 | APPLICANT |
| Applicant returned to address corrections | 4/20/2022 | SAM CHANG |
| Plan Check Approved | 4/22/2022 | SAM CHANG |
| Issued | 4/26/2022 | APPLICANT |
| Permit Finaled | 10/26/2023 | JONATHAN HOM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | RENZ SORIANO |
| Stormwater Pollution Mitigatn | Cleared | 12/14/2021 | MARTIN FRAGOSO |
| Excavation more than 5-ft deep | Cleared | 4/7/2022 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 4/12/2022 | JOSE RODRIGUEZ |
Contact Information
| Contractor | Calex Engineering Company; Lic. No.: 1035841-A | 23651 PINE STREET NEWHALL, CA 91321 |
| Engineer | Cefali,, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 4/27/2022 | Approved | MATTHEW JENKINS |
| Deputy Grading | 6/21/2022 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 6/22/2022 | Conditional Approval | MATTHEW JENKINS |
| Deputy Grading | 7/1/2022 | Conditional Approval | MATTHEW JENKINS |
| Bottom/Toe | 7/5/2022 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 7/20/2022 | Approved | ALEXANDER HELFER |
| Final | 10/18/2023 | Partial Inspection | JONATHAN HOM |
| Rough | 10/18/2023 | Partial Inspection | JONATHAN HOM |
| Final | 10/26/2023 | Permit Finaled | JONATHAN HOM |
| Rough | 10/26/2023 | Approved | JONATHAN HOM |