188 N HOMEWOOD ROAD 90049

Certificate Information: 188 N HOMEWOOD ROAD 90049

Application / Permit
21030-10000-03940
Plan Check / Job No.
B21LA11275
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING FOR A NEW 2-STORY SFD W/ ATTACHED GARAGE AND BASEMENT.
Permit Issued
Issued on 2/25/2022
Issuing Office
Current Status
Permit Finaled on 3/3/2025

Permit Application Status History

Submitted 6/18/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 MAHNAZ NOURHASHEMI
Corrections Issued 7/9/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 7/22/2021 ALLEN MANALANSAN
Applicant returned to address corrections 10/4/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 2/23/2022 MAHNAZ NOURHASHEMI
Issued 2/25/2022 APPLICANT
Building Plans Picked Up 3/2/2022 APPLICANT
Permit Finaled 2/28/2025 MATTHEW JENKINS

Permit Application Clearance Information

Watercourse Cleared 8/5/2021 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 8/10/2021 CATHERINE ADROVER
Excavation more than 5-ft deep Cleared 10/4/2021 CALOSHA APPROVED
GPI Written Notices Cleared 10/5/2021 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 10/5/2021 MAHNAZ NOURHASHEMI

Contact Information

Architect Kang,, Everitt; Lic. No.: C31873 29222 DAKOTA DRIVE      VALENCIA, CA 91354
Contractor G3 Urban; Lic. No.: 1040756-B 15235 S WESTERN AVE      GARDENA, CA 90249
Engineer Eosakul,, Dissakorn; Lic. No.: S5226 8363 EDGEWOOD ST      CHINO, CA 91708

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 6/6/2022 Approved CHARLES POWELL
Sub-Drain 10/27/2022 Partial Inspection JONATHAN HOM
Sub-Drain 10/28/2022 Approved CHARLES POWELL
Sub-Drain 5/11/2023 Approved VASIL MIHALEV
Approved Compaction Report 9/12/2023 Partial Approval CHARLES POWELL
Rough 1/3/2025 Corrections Issued MATTHEW JENKINS
Bottom/Toe 2/12/2025 Approved JOHNNY MIRANDA
FLOOD-Proofing Certificate 2/12/2025 Approved JOHNNY MIRANDA
Final 2/12/2025 Not Ready for Inspection JOHNNY MIRANDA
Rough 2/12/2025 Not Ready for Inspection JOHNNY MIRANDA
Special/Order Compliance 2/14/2025 Partial Inspection JOHNNY MIRANDA
Final 2/18/2025 Not Ready for Inspection MATTHEW JENKINS
Rough 2/18/2025 Not Ready for Inspection MATTHEW JENKINS
Approved Compaction Report 2/19/2025 Corrections Issued MATTHEW JENKINS
Final 2/20/2025 Not Ready for Inspection MATTHEW JENKINS
Rough 2/20/2025 Not Ready for Inspection MATTHEW JENKINS
Approved Compaction Report 2/27/2025 Approved MATTHEW JENKINS
Final 2/28/2025 Permit Finaled MATTHEW JENKINS
Rough 2/28/2025 Approved MATTHEW JENKINS