1600 E VENICE BLVD 90291

Certificate Information: 1600 E VENICE BLVD 90291

Application / Permit
21030-10000-03931
Plan Check / Job No.
B21LA11261
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
Site grading for construction of new apartment with subterrenean parking garage
Permit Issued
Issued on 8/9/2022
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 7/22/2025

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 VU NGUYEN
Corrections Issued 6/22/2021 VU NGUYEN
Quality Review Completed 6/23/2021 EUGENE BARBEAU
Applicant returned to address corrections 6/6/2022 VU NGUYEN
Plan Check Approved 8/3/2022 VU NGUYEN
Issued 8/9/2022 APPLICANT
Permit Finaled 7/17/2025 AL GAMBLE

Permit Application Clearance Information

"Q" conditions Cleared 4/18/2022 RYAN LY
Miscellaneous Cleared 4/18/2022 RYAN LY
Miscellaneous Cleared 4/18/2022 RYAN LY
Miscellaneous Cleared 4/18/2022 RYAN LY
Miscellaneous Cleared 4/18/2022 RYAN LY
Miscellaneous Cleared 4/18/2022 RYAN LY
Specific Plan Cleared 6/7/2022 PEDRO AYALA
Work Adjacent to Public Way Cleared 7/22/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 7/29/2022 KATHLEEN LEE
Excavation more than 5-ft deep Cleared 8/3/2022 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Downey,, Henry Ross; Lic. No.: C30372 7463 VARNA AVE      NORTH HOLLYWOOD, CA 916054011
Engineer Mahmoudkhani,, Behnam; Lic. No.: C88488 120 W WILSON AVE 1550      GLENDALE, CA 91203

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 8/17/2022 Approved TIMOTHY POWELL
Bottom/Toe 10/26/2022 Not Ready for Inspection AL GAMBLE
Rough 10/26/2022 Not Ready for Inspection AL GAMBLE
Fill/Backfill 11/1/2022 Partial Inspection AL GAMBLE
Rough 11/1/2022 Partial Inspection AL GAMBLE
Drainage Devices/Catch Basin 11/3/2022 Partial Approval AL GAMBLE
Sub-Drain 11/4/2022 Partial Approval JONATHAN HOM
Rough 1/18/2023 Partial Approval AL GAMBLE
Sub-Drain 1/18/2023 Partial Approval AL GAMBLE
Rough 1/25/2023 Partial Inspection MATTHEW JENKINS
Sub-Drain 1/25/2023 Partial Approval MATTHEW JENKINS
Rough 2/6/2023 Partial Approval MATTHEW JENKINS
Rough 3/8/2023 Partial Approval MATTHEW JENKINS
Sub-Drain 3/8/2023 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 5/14/2024 Approved MATTHEW JENKINS
Initial Grading 10/25/2024 Partial Inspection AL GAMBLE
Rough 10/29/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 7/17/2025 Not Ready for Inspection AL GAMBLE
Final 7/17/2025 Permit Finaled AL GAMBLE
Rough 7/17/2025 Approved AL GAMBLE