8141 S GULANA AVE 90293
Certificate Information: 8141 S GULANA AVE 90293
- Application / Permit
- 21030-10000-03534
- Plan Check / Job No.
- B21LA10287
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING TO BACKFILL REMOVAL OF CELLAR WALLS ELLIOT -1 & L-1. BACKFILL WITH CLSM PER IB/P/BC 2020-121
- Permit Issued
- Issued on 10/10/2023
- Issuing Office
- Current Status
- Permit Finaled on 3/7/2024
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | LAMAR DAVIS |
| Corrections Issued | 6/28/2021 | LAMAR DAVIS |
| Quality Review Completed | 7/20/2021 | WING SUEN |
| Building Plans Picked Up | 7/22/2021 | APPLICANT |
| Applicant returned to address corrections | 9/7/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 9/15/2023 | ADRIANA LOPEZ |
| No Progress | 9/15/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 9/15/2023 | ADRIANA LOPEZ |
| Issued | 10/10/2023 | APPLICANT |
| Permit Finaled | 3/6/2024 | AL GAMBLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/27/2023 | BRIAN MILLER |
| Coastal Zone | Cleared | 7/6/2023 | NOAH MCCOY |
| ZA Case | Cleared | 7/6/2023 | NOAH MCCOY |
| Abandoned oil well | Cleared | 9/12/2023 | KURT CORRAL |
| Excavation more than 5-ft deep | Cleared | 10/10/2023 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Conkle,, Christopher Sanford; Lic. No.: GE2926 | 1031 S BROADWAY STE 300 LOS ANGELES, CA 90015 |
Inspector Information
| JESUS RODRIGUEZ, (213) 216-1187 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/12/2023 | Approved | AL GAMBLE |
| Bottom/Toe | 10/19/2023 | Partial Approval | AL GAMBLE |
| Excavation | 10/19/2023 | Partial Approval | AL GAMBLE |
| Bottom/Toe | 10/26/2023 | Not Ready for Inspection | AL GAMBLE |
| Excavation | 10/26/2023 | Not Ready for Inspection | AL GAMBLE |
| Excavation | 10/27/2023 | Partial Inspection | AL GAMBLE |
| Rough | 10/27/2023 | Partial Inspection | AL GAMBLE |
| Excavation | 10/30/2023 | Not Ready for Inspection | AL GAMBLE |
| Initial Grading | 10/30/2023 | Not Ready for Inspection | AL GAMBLE |
| Bottom/Toe | 11/1/2023 | Partial Approval | AL GAMBLE |
| Excavation | 11/1/2023 | Partial Approval | AL GAMBLE |
| Bottom/Toe | 11/20/2023 | Partial Approval | AL GAMBLE |
| Excavation | 11/20/2023 | Approved | AL GAMBLE |
| Bottom/Toe | 11/22/2023 | Corrections Issued | MATTHEW JENKINS |
| Excavation | 11/22/2023 | Partial Inspection | MATTHEW JENKINS |
| Rough | 11/22/2023 | Partial Inspection | MATTHEW JENKINS |
| Excavation | 11/28/2023 | Partial Approval | AL GAMBLE |
| Fill/Backfill | 11/28/2023 | Corrections Issued | AL GAMBLE |
| Bottom/Toe | 12/7/2023 | Partial Approval | AL GAMBLE |
| Excavation | 12/7/2023 | Partial Approval | AL GAMBLE |
| Excavation | 12/11/2023 | Partial Inspection | AL GAMBLE |
| Bottom/Toe | 12/12/2023 | Partial Inspection | AL GAMBLE |
| Excavation | 12/12/2023 | Partial Inspection | AL GAMBLE |
| Excavation | 12/13/2023 | Partial Approval | AL GAMBLE |
| Excavation | 12/26/2023 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 1/19/2024 | Approved | VASIL MIHALEV |
| Final | 1/19/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Rough | 1/19/2024 | Approved | VASIL MIHALEV |
| Final | 1/25/2024 | Partial Approval | AL GAMBLE |
| Final | 2/21/2024 | Not Ready for Inspection | AL GAMBLE |
| Final | 2/29/2024 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 3/6/2024 | Permit Finaled | AL GAMBLE |