20024 W CHASE ST 91306

Certificate Information: 20024 W CHASE ST 91306

Application / Permit
21030-10000-03494
Plan Check / Job No.
G21LA00117
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
TRACT GRADING FOR (9) LOT SMALL SUBDIVISION PER VTT-82646-SL. CUT = 1,077 CY; FILL = 4,560 CY; R&R = 2,745 CY, IMPORT = 738 CY.
Permit Issued
Issued on 4/18/2022
Issuing Office
Current Status
Permit Finaled on 4/30/2025

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 6/28/2021 DAN RYAN EVANGELISTA
Corrections Issued 6/28/2021 DAN RYAN EVANGELISTA
Applicant returned to address corrections 10/13/2021 DAN RYAN EVANGELISTA
Plan Check Approved 4/18/2022 DAN RYAN EVANGELISTA
Issued 4/18/2022 APPLICANT
Permit Finaled 4/29/2025 GERMAN RODRIGUEZ MENDOZA

Permit Application Clearance Information

Permit Cleared 7/31/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/31/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/3/2021 LEE GUILBEAUX
Low Impact Development Cleared 9/24/2021 AMMAR ELTAWIL
Stormwater Pollution Mitigatn Cleared 9/24/2021 AMMAR ELTAWIL
Disturb/Remove Protected Trees Cleared 10/28/2021 ADALBERTO VERA
Tract Map conditions Cleared 11/10/2021 NOAH MCCOY
"Q" conditions Cleared 11/17/2021 NOAH MCCOY
"T" removal Cleared 11/17/2021 NOAH MCCOY

Contact Information

Contractor Inland Developement; Lic. No.: 828225-B 1232 VILLAGE WAY STE A      SANTA ANA, CA 92705
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Mar,, Larry L; Lic. No.: C55069 4425 BEULAH DR      LA CANADA, CA 91011

Inspector Information

ALEXANDER HELFER, (818) 374-4354 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 5/11/2022 Partial Approval BRIAN MILLER
Excavation 5/11/2022 Partial Approval BRIAN MILLER
Initial Grading 5/11/2022 Approved BRIAN MILLER
Bottom/Toe 5/18/2022 Partial Approval BRIAN MILLER
Excavation 5/18/2022 Partial Approval BRIAN MILLER
Fill/Backfill 5/18/2022 Partial Approval BRIAN MILLER
Bottom/Toe 5/24/2022 Partial Approval BRIAN MILLER
Bottom/Toe 6/3/2022 Partial Approval BRIAN MILLER
Approved Compaction Report 7/18/2022 Approved BRIAN MILLER
Bottom/Toe 4/25/2025 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 4/25/2025 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Rough 4/25/2025 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
SUSMP-Std. Urban Storm Water 4/25/2025 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Bottom/Toe 4/29/2025 Approved GERMAN RODRIGUEZ MENDOZA
Final 4/29/2025 Permit Finaled GERMAN RODRIGUEZ MENDOZA
Rough 4/29/2025 Approved GERMAN RODRIGUEZ MENDOZA
SUSMP-Std. Urban Storm Water 4/29/2025 Approved GERMAN RODRIGUEZ MENDOZA