8225 W MULHOLLAND DR 90046
Certificate Information: 8225 W MULHOLLAND DR 90046
- Application / Permit
- 21030-10000-03488
- Plan Check / Job No.
- B21LA10153
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- BACKFILLING SWIMMING POOL WITH CERTIFIED FILL (REMOVE POOL SHELL). 160 C.Y. GPI #21030-30000-01110
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/22/2022
Permit Application Status History
| Submitted | 5/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2021 | JESSE JIMENEZ |
| Corrections Issued | 6/1/2021 | JESSE JIMENEZ |
| Plan Check Approved | 6/11/2021 | JESSE JIMENEZ |
| Issued | 6/21/2021 | APPLICANT |
| Building Plans Picked Up | 6/22/2021 | APPLICANT |
| Permit Finaled | 9/22/2022 | MANUEL TEJADA |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/3/2021 | MINDY NGUYEN |
Contact Information
| Contractor | Jimenez Demolition Inc; Lic. No.: 872188-C21 | PO BOX 3310 SOUTH PASADENA, CA 91031 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 6/30/2021 | Corrections Issued | MANUEL TEJADA |
| Bottom/Toe | 7/16/2021 | Not Ready for Inspection | MANUEL TEJADA |
| Bottom/Toe | 10/12/2021 | Partial Approval | TIMOTHY POWELL |
| Bottom/Toe | 11/22/2021 | Approved | TIMOTHY POWELL |
| Final | 11/22/2021 | Not Ready for Inspection | TIMOTHY POWELL |
| Rough | 11/22/2021 | Approved | TIMOTHY POWELL |
| Approved Compaction Report | 12/21/2021 | Approved | TIMOTHY POWELL |
| Final | 9/22/2022 | Permit Finaled | MANUEL TEJADA |