14061 W ROSCOE BLVD 91402

Certificate Information: 14061 W ROSCOE BLVD 91402

Application / Permit
21030-10000-03182
Plan Check / Job No.
B21LA09234
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
Site grading for new buildings under 19010-10000-00179 and 19010-10000-00180 including parking re-stripe.
Permit Issued
Issued on 5/4/2022
Issuing Office
Current Status
Permit Finaled on 4/27/2026

Permit Application Status History

Submitted 5/17/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 ARMEN JIVALAGIAN
Green Plans Picked Up 6/4/2021 APPLICANT
Corrections Issued 6/22/2021 ARMEN JIVALAGIAN
Quality Review Completed 6/24/2021 PETER KIM
Building Plans Picked Up 6/29/2021 APPLICANT
Disabled Access Plans Picked Up 7/6/2021 APPLICANT
Applicant returned to address corrections 8/5/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/11/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/20/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/2/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/3/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/8/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/9/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/15/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/16/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/17/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 10/4/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 10/20/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/29/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/11/2022 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/21/2022 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/19/2022 ARMEN JIVALAGIAN
Plan Check Approved 4/28/2022 ARMEN JIVALAGIAN
Issued 5/4/2022 APPLICANT
Permit Finaled 4/24/2026 MATTHEW JENKINS

Permit Application Clearance Information

CPC Cleared 1/14/2022 JASON CHAN

Contact Information

Contractor T G Construction Inc; Lic. No.: 528058-B 139 NEVADA ST      EL SEGUNDO, CA 90245
Engineer Ahmed,, Zafar; Lic. No.: GE2720 113 TOMATO SPRINGS      IRVINE, CA 92618
Engineer Aoanan,, Virgilio Cendana; Lic. No.: C36079 1041 S GARFIELD AVE STE #210      ALHAMBRA, CA 91801
Engineer Fitzgerald,, Shane Scott; Lic. No.: S4757 950 S GRAND AVE 4TH FL      LOS ANGELES, CA 90015

Inspector Information

ALEXANDER HELFER, (818) 374-4354 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 5/6/2022 Approved MANUEL TEJADA
Bottom/Toe 5/10/2022 Partial Approval BRIAN MILLER
Bottom/Toe 5/17/2022 Partial Approval BRIAN MILLER
Bottom/Toe 5/23/2022 No Access for Inspection BRIAN MILLER
Bottom/Toe 5/26/2022 Approved BRIAN MILLER
Excavation 6/9/2022 Partial Inspection BRIAN MILLER
Approved Compaction Report 6/22/2022 Approved BRIAN MILLER
Approved Compaction Report 7/8/2022 Approved BRIAN MILLER
Excavation 7/15/2022 Partial Approval BRIAN MILLER
Approved Compaction Report 8/26/2022 Approved BRIAN MILLER
Drainage Devices/Catch Basin 8/30/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 9/2/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 9/9/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 9/15/2022 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 9/21/2022 Partial Inspection MANUEL TEJADA
Drainage Devices/Catch Basin 9/27/2022 Partial Approval MANUEL TEJADA
Drainage Devices/Catch Basin 10/5/2022 Partial Approval MANUEL TEJADA
Drainage Devices/Catch Basin 11/30/2022 Partial Approval MANUEL TEJADA
Drainage Devices/Catch Basin 12/7/2022 Partial Approval LANNY MERRICK
Drainage Devices/Catch Basin 12/8/2022 Partial Approval LANNY MERRICK
Drainage Devices/Catch Basin 12/9/2022 Partial Approval LANNY MERRICK
Drainage Devices/Catch Basin 4/17/2023 Partial Inspection BRIAN MILLER
Drainage Devices/Catch Basin 4/20/2023 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 6/21/2023 Partial Approval MANUEL TEJADA
Drainage Devices/Catch Basin 6/27/2023 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 7/13/2023 Partial Approval BRIAN MILLER
Drainage Devices/Catch Basin 7/26/2023 Partial Approval MANUEL TEJADA
Drainage Devices/Catch Basin 10/13/2023 Partial Approval MANUEL TEJADA
Drainage Devices/Catch Basin 6/25/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Rough 6/25/2024 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Drainage Devices/Catch Basin 7/1/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Rough 7/1/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Final 4/24/2026 Permit Finaled MATTHEW JENKINS
Rough 4/24/2026 Approved MATTHEW JENKINS