2710 E MEDIA CENTER DR 90065
Certificate Information: 2710 E MEDIA CENTER DR 90065
- Application / Permit
- 21030-10000-03145
- Plan Check / Job No.
- B21LA09101
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- MINOR WORK TO SUPPORT THE CMU ENCLOSURE HOUSING A GENERATOR. GRADING PERMIT WITH SOIL REPORT. MINOR EXCAVATION FOR WALL FOOTINGS AND GENERATOR PAD. ASPHALT PATCHING TO MATCH EXISTING
- Permit Issued
- Issued on 10/25/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/8/2022
Permit Application Status History
| Submitted | 5/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2021 | FERNANDO FLORES |
| Corrections Issued | 5/15/2021 | FERNANDO FLORES |
| Plan Check Approved | 10/7/2021 | TSE MING HUANG |
| Issued | 10/25/2021 | APPLICANT |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| Permit Finaled | 4/7/2022 | LANNY MERRICK |
Permit Application Clearance Information
| Supp. Use District POD/CDO/TDO | Cleared | 6/11/2021 | ADRINEH MELKONIAN |
| Low Impact Development | Cleared | 8/6/2021 | MITESH PATEL |
| Excavation more than 5-ft deep | Cleared | 8/10/2021 | CALOSHA APPROVED |
| Metro Rail approval | Cleared | 8/10/2021 | MTA APPROVED |
Contact Information
| Architect | Laylon,, Stephanie Marie; Lic. No.: C23660 | 2912 ARREOS SAN CLEMENTE, CA 92673 |
| Contractor | Summer Systems Inc; Lic. No.: 560229-B | 28942 HANCOCK PARKWAY VALENCIA, CA 91355 |
| Engineer | Mitchell,, Gregory K; Lic. No.: GE2364 | 22885 E SAVI RANCH PKWY STE E YORBA LINDA, CA 92887 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 11/18/2021 | Approved | ROBERT HUGHES |
| Bottom/Toe | 11/24/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Excavation | 12/6/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Grading | 12/9/2021 | Approved | ROBERT HUGHES |
| Bottom/Toe | 12/17/2021 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 12/22/2021 | Approved | ROBERT HUGHES |
| Approved Compaction Report | 1/12/2022 | Approved | ROBERT HUGHES |
| Excavation | 1/18/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Final | 4/7/2022 | Permit Finaled | LANNY MERRICK |
| Rough | 4/7/2022 | Approved | LANNY MERRICK |