845 W 79TH ST 90044
Certificate Information: 845 W 79TH ST 90044
- Application / Permit
- 21030-10000-02444
- Plan Check / Job No.
- B20LA11770
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING REMOVEAL AND RECOMPACT FOR NEW SFD AND DUPLEX UNDER 20010-10000-02271 AND 20010-10000-02272. [R&R 162 C.Y.]
- Permit Issued
- Issued on 6/4/2021
- Issuing Office
- Current Status
- Permit Finaled on 5/3/2022
Permit Application Status History
| Submitted | 7/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2020 | ARMEN JIVALAGIAN |
| Corrections Issued | 7/28/2020 | ARMEN JIVALAGIAN |
| Quality Review Completed | 7/30/2020 | CHAD DOI |
| Building Plans Picked Up | 8/6/2020 | APPLICANT |
| Applicant returned to address corrections | 1/5/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/8/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 4/9/2021 | ARMEN JIVALAGIAN |
| Plan Check Approved | 6/4/2021 | ARMEN JIVALAGIAN |
| Issued | 6/4/2021 | APPLICANT |
| Permit Finaled | 4/29/2022 | KIRK LINKLATER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-B | 3627 E FIRST STREET LOS ANGELES, CA 90063 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
| Engineer | Sanchez,, Pablo Beltran; Lic. No.: C86223 | 1840 S GAFFEY ST 382 SAN PEDRO, CA 90731 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 6/7/2021 | Approved | VASIL MIHALEV |
| Initial Grading | 6/7/2021 | Approved | VASIL MIHALEV |
| Bottom/Toe | 6/11/2021 | Approved | VASIL MIHALEV |
| Final | 6/14/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Rough | 6/14/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Approved Compaction Report | 7/2/2021 | Corrections Issued | TIMOTHY POWELL |
| Approved Compaction Report | 7/15/2021 | Approved | TIMOTHY POWELL |
| Final | 4/21/2022 | Corrections Issued | MATTHEW JENKINS |
| Rough | 4/21/2022 | Approved | MATTHEW JENKINS |
| Final | 4/28/2022 | Not Ready for Inspection | JONATHAN HOM |
| Final | 4/29/2022 | Permit Finaled | KIRK LINKLATER |