18412 W OXNARD ST 91356

Certificate Information: 18412 W OXNARD ST 91356

Application / Permit
21030-10000-02055
Plan Check / Job No.
B21LA05776
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
ROUGH GRADING FOR A NEW COMERCIAL MANUFACTURING BUILDING FOR CELL-THERAPY PRODUCTS- UNDER PERMIT APPLICATION NO. 21010-10000-00719.
Permit Issued
Issued on 8/17/2021
Issuing Office
Current Status
Permit Finaled on 12/29/2022

Permit Application Status History

Submitted 4/5/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 KESETE HAREGOT
Plans on Hold 4/15/2021 BILL STUTSMAN
Hold Released 5/6/2021 BILL STUTSMAN
Corrections Issued 5/24/2021 KESETE HAREGOT
Quality Review Completed 5/24/2021 FARUK SEZER
Building Plans Picked Up 5/25/2021 APPLICANT
Disabled Access Plans Picked Up 5/25/2021 APPLICANT
Plan Check Approved 8/16/2021 KESETE HAREGOT
Issued 8/17/2021 APPLICANT
Permit Finaled 12/29/2022 MICHAEL TEMPLE

Permit Application Clearance Information

Address approval Cleared 6/1/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/1/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 6/1/2021 GABRIEL ROBLES
Work Adjacent to Public Way Cleared 6/1/2021 GABRIEL ROBLES
Metro Rail approval Cleared 6/10/2021 KESETE HAREGOT
DAS Clearance Cleared 6/24/2021 SHINE LIN

Contact Information

Contractor Turner Construction Company; Lic. No.: 210639-B 1900 S STATE COLLEGE BLVD   STE 150    ANAHEIM, CA 92806
Engineer Gavazza,, Jeffrey Bryan; Lic. No.: C59894 472 35TH ST      MANHATTAN BEACH, CA 90266
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Approved Compaction Report 8/26/2021 Not Ready for Inspection ALEXANDER ANDREWS
Bottom/Toe 8/26/2021 Not Ready for Inspection ALEXANDER ANDREWS
Final 8/26/2021 Not Ready for Inspection ALEXANDER ANDREWS
Initial Grading 8/26/2021 Approved ALEXANDER ANDREWS
Rough 8/26/2021 Not Ready for Inspection ALEXANDER ANDREWS
Initial Grading 11/8/2021 Approved ALEXANDER ANDREWS
Drainage Devices/Catch Basin 7/6/2022 Approved VASIL MIHALEV
Fill/Backfill 7/6/2022 Conditional Approval VASIL MIHALEV
Fill/Backfill 7/21/2022 Partial Approval LANNY MERRICK
Initial Grading 10/12/2022 Not Ready for Inspection LANNY MERRICK
Drainage Devices/Catch Basin 10/27/2022 Approved ALEXANDER HELFER
Fill/Backfill 10/27/2022 Approved ALEXANDER HELFER
Initial Grading 11/1/2022 Partial Inspection MANUEL TEJADA
Fill/Backfill 11/15/2022 Partial Inspection TIMOTHY POWELL
Drainage Devices/Catch Basin 11/21/2022 Partial Approval TIMOTHY POWELL
Drainage Devices/Catch Basin 11/30/2022 Partial Inspection LANNY MERRICK
Approved Compaction Report 12/16/2022 Not Ready for Inspection LANNY MERRICK
Bottom/Toe 12/16/2022 Not Ready for Inspection LANNY MERRICK
Final 12/16/2022 Not Ready for Inspection LANNY MERRICK
Rough 12/16/2022 Not Ready for Inspection LANNY MERRICK
Approved Compaction Report 12/29/2022 Approved ALEXANDER HELFER
Bottom/Toe 12/29/2022 Approved MICHAEL TEMPLE
Final 12/29/2022 Permit Finaled MICHAEL TEMPLE