627 S CATALINA ST 90005
Certificate Information: 627 S CATALINA ST 90005
- Application / Permit
- 21030-10000-01172
- Plan Check / Job No.
- B21LA03252
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE PREPARATION & EXCAVATION & REMOVAL & RECOMPACTION .(TOTAL2500 CY)
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Current Status
- Permit Finaled on 9/9/2025
Permit Application Status History
| Submitted | 2/24/2021 | APPLICANT |
| Building Plans Picked Up | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | GARO TELMI |
| Corrections Issued | 4/1/2021 | GARO TELMI |
| Disabled Access Plans Picked Up | 4/8/2021 | APPLICANT |
| Quality Review Completed | 4/12/2021 | KEN GILL |
| Green Plans Picked Up | 4/27/2021 | APPLICANT |
| Applicant returned to address corrections | 6/14/2021 | GARO TELMI |
| Applicant returned to address corrections | 7/15/2021 | GARO TELMI |
| Applicant returned to address corrections | 7/22/2021 | GARO TELMI |
| Applicant returned to address corrections | 8/12/2021 | GARO TELMI |
| Applicant returned to address corrections | 8/19/2021 | GARO TELMI |
| Applicant returned to address corrections | 9/14/2021 | GARO TELMI |
| Applicant returned to address corrections | 9/23/2021 | GARO TELMI |
| Applicant returned to address corrections | 10/4/2021 | GARO TELMI |
| Applicant returned to address corrections | 10/18/2021 | GARO TELMI |
| Applicant returned to address corrections | 10/28/2021 | GARO TELMI |
| Applicant returned to address corrections | 11/30/2021 | GARO TELMI |
| Applicant returned to address corrections | 12/1/2021 | GARO TELMI |
| Applicant returned to address corrections | 2/15/2022 | GARO TELMI |
| Applicant returned to address corrections | 5/24/2022 | GARO TELMI |
| Applicant returned to address corrections | 6/7/2022 | GARO TELMI |
| Plan Check Approved | 7/21/2022 | GARO TELMI |
| Issued | 7/27/2022 | APPLICANT |
| Permit Finaled | 9/8/2025 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 9/30/2021 | CALOSHA APPROVED |
| Tract Map conditions | Cleared | 10/7/2021 | RICHARD REASER |
| Construction near power lines | Cleared | 12/22/2021 | WALTER RAMIREZ |
| "Q" conditions | Cleared | 2/10/2022 | RICHARD REASER |
| CPC | Cleared | 2/10/2022 | RICHARD REASER |
| Metro Rail approval | Cleared | 2/18/2022 | GARO TELMI |
| Low Impact Development | Cleared | 4/8/2022 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 4/20/2022 | THAN WIN |
| Work Adjacent to Public Way | Cleared | 5/16/2022 | JOSE RODRIGUEZ |
| "T" removal | Cleared | 6/22/2022 | RYAN LY |
| Redevelopment Project Area | Cleared | 6/30/2022 | DAVID URITA |
Contact Information
| Contractor | Arco National Holdings Inc; Lic. No.: 1072592-B | 900 N ROCK HILL RD SAINT LOUIS, MO 63119 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 1/12/2024 | Partial Approval | LANNY MERRICK |
| Deputy Grading | 1/16/2024 | Partial Approval | LANNY MERRICK |
| Deputy Grading | 1/17/2024 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/18/2024 | Conditional Approval | MICHAEL TEMPLE |
| Deputy Grading | 1/19/2024 | Conditional Approval | RUSSELL BONVOULOIR |
| Rough | 9/16/2024 | Corrections Issued | RUSSELL BONVOULOIR |
| Approved Compaction Report | 9/23/2024 | Approved | LANNY MERRICK |
| Bottom/Toe | 9/8/2025 | Approved | RUSSELL BONVOULOIR |
| Final | 9/8/2025 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 9/8/2025 | Approved | RUSSELL BONVOULOIR |