620 E 249TH ST 90744
Certificate Information: 620 E 249TH ST 90744
- Application / Permit
- 21030-10000-00919
- Plan Check / Job No.
- B21LA02530
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING SITE PREPARATION FOR THE NEW CONSTRUCTION OF EDUCATIONAL BUILDINGS.
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- Permit Finaled on 3/7/2023
Permit Application Status History
| Submitted | 2/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | JOHNNY WU |
| Plans on Hold | 2/18/2021 | BILL STUTSMAN |
| Green Plans Picked Up | 3/9/2021 | APPLICANT |
| Hold Released | 4/8/2021 | BILL STUTSMAN |
| Corrections Issued | 4/20/2021 | JOHNNY WU |
| Quality Review Completed | 4/22/2021 | FARUK SEZER |
| Disabled Access Plans Picked Up | 5/17/2021 | APPLICANT |
| Applicant returned to address corrections | 5/21/2021 | JOHNNY WU |
| Applicant returned to address corrections | 9/16/2021 | JOHNNY WU |
| Applicant returned to address corrections | 9/24/2021 | JOHNNY WU |
| Applicant returned to address corrections | 11/16/2021 | JOHNNY WU |
| Applicant returned to address corrections | 1/4/2022 | JOHNNY WU |
| Plan Check Approved | 1/4/2022 | JOHNNY WU |
| Issued | 1/4/2022 | APPLICANT |
| Building Plans Picked Up | 3/7/2022 | APPLICANT |
| Permit Finaled | 3/1/2023 | AL GAMBLE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Del Amo Construction Inc; Lic. No.: 744458-B | 23840 MADISON STREET TORRANCE, CA 90505 |
| Engineer | Hill,, Edward Foster; Lic. No.: GE2126 | 27865 AMBERWOOD LANE VALENCIA, CA 91354 |
| Engineer | Wang,, Guan; Lic. No.: C79702 | 135 N SAN GABRIEL BLVD SAN GABRIEL, CA 91775 |
Inspector Information
| JESUS RODRIGUEZ, (213) 216-1187 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 1/6/2022 | Approved | JONATHAN HOM |
| Bottom/Toe | 1/12/2022 | Conditional Approval | JONATHAN HOM |
| Excavation | 1/12/2022 | Partial Inspection | JONATHAN HOM |
| Rough | 1/13/2022 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 1/19/2022 | Partial Inspection | JONATHAN HOM |
| Rough | 1/25/2022 | Partial Inspection | JONATHAN HOM |
| Approved Compaction Report | 2/14/2022 | Approved | VASIL MIHALEV |
| Bottom/Toe | 2/14/2022 | Not Ready for Inspection | JONATHAN HOM |
| Final | 2/14/2022 | Not Ready for Inspection | JONATHAN HOM |
| Rough | 2/14/2022 | Not Ready for Inspection | JONATHAN HOM |
| Approved Compaction Report | 3/7/2022 | Approved | JONATHAN HOM |
| Drainage Devices/Catch Basin | 7/8/2022 | No Result Entered | JONATHAN HOM |
| Sub-Drain | 7/8/2022 | Partial Approval | JONATHAN HOM |
| Sub-Drain | 7/11/2022 | Partial Approval | JONATHAN HOM |
| Sub-Drain | 7/12/2022 | Not Ready for Inspection | JONATHAN HOM |
| Fill/Backfill | 7/13/2022 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 7/15/2022 | Partial Approval | JONATHAN HOM |
| Sub-Drain | 7/15/2022 | Partial Inspection | JONATHAN HOM |
| Drainage Devices/Catch Basin | 7/21/2022 | Partial Approval | MICHAEL TEMPLE |
| Bottom/Toe | 8/9/2022 | Not Ready for Inspection | JONATHAN HOM |
| Final | 8/9/2022 | Partial Inspection | JONATHAN HOM |
| Rough | 8/9/2022 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 8/16/2022 | Approved | JONATHAN HOM |
| Final | 8/16/2022 | Partial Approval | JONATHAN HOM |
| Rough | 8/16/2022 | Approved | JONATHAN HOM |
| Final | 3/1/2023 | Permit Finaled | AL GAMBLE |