620 E 249TH ST 90744

Certificate Information: 620 E 249TH ST 90744

Application / Permit
21030-10000-00919
Plan Check / Job No.
B21LA02530
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
GRADING SITE PREPARATION FOR THE NEW CONSTRUCTION OF EDUCATIONAL BUILDINGS.
Permit Issued
Issued on 1/4/2022
Issuing Office
Current Status
Permit Finaled on 3/7/2023

Permit Application Status History

Submitted 2/12/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 JOHNNY WU
Plans on Hold 2/18/2021 BILL STUTSMAN
Green Plans Picked Up 3/9/2021 APPLICANT
Hold Released 4/8/2021 BILL STUTSMAN
Corrections Issued 4/20/2021 JOHNNY WU
Quality Review Completed 4/22/2021 FARUK SEZER
Disabled Access Plans Picked Up 5/17/2021 APPLICANT
Applicant returned to address corrections 5/21/2021 JOHNNY WU
Applicant returned to address corrections 9/16/2021 JOHNNY WU
Applicant returned to address corrections 9/24/2021 JOHNNY WU
Applicant returned to address corrections 11/16/2021 JOHNNY WU
Applicant returned to address corrections 1/4/2022 JOHNNY WU
Plan Check Approved 1/4/2022 JOHNNY WU
Issued 1/4/2022 APPLICANT
Building Plans Picked Up 3/7/2022 APPLICANT
Permit Finaled 3/1/2023 AL GAMBLE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Del Amo Construction Inc; Lic. No.: 744458-B 23840 MADISON STREET      TORRANCE, CA 90505
Engineer Hill,, Edward Foster; Lic. No.: GE2126 27865 AMBERWOOD LANE      VALENCIA, CA 91354
Engineer Wang,, Guan; Lic. No.: C79702 135 N SAN GABRIEL BLVD      SAN GABRIEL, CA 91775

Inspector Information

JESUS RODRIGUEZ, (213) 216-1187 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/6/2022 Approved JONATHAN HOM
Bottom/Toe 1/12/2022 Conditional Approval JONATHAN HOM
Excavation 1/12/2022 Partial Inspection JONATHAN HOM
Rough 1/13/2022 Partial Approval JONATHAN HOM
Bottom/Toe 1/19/2022 Partial Inspection JONATHAN HOM
Rough 1/25/2022 Partial Inspection JONATHAN HOM
Approved Compaction Report 2/14/2022 Approved VASIL MIHALEV
Bottom/Toe 2/14/2022 Not Ready for Inspection JONATHAN HOM
Final 2/14/2022 Not Ready for Inspection JONATHAN HOM
Rough 2/14/2022 Not Ready for Inspection JONATHAN HOM
Approved Compaction Report 3/7/2022 Approved JONATHAN HOM
Drainage Devices/Catch Basin 7/8/2022 No Result Entered JONATHAN HOM
Sub-Drain 7/8/2022 Partial Approval JONATHAN HOM
Sub-Drain 7/11/2022 Partial Approval JONATHAN HOM
Sub-Drain 7/12/2022 Not Ready for Inspection JONATHAN HOM
Fill/Backfill 7/13/2022 Partial Approval JONATHAN HOM
Drainage Devices/Catch Basin 7/15/2022 Partial Approval JONATHAN HOM
Sub-Drain 7/15/2022 Partial Inspection JONATHAN HOM
Drainage Devices/Catch Basin 7/21/2022 Partial Approval MICHAEL TEMPLE
Bottom/Toe 8/9/2022 Not Ready for Inspection JONATHAN HOM
Final 8/9/2022 Partial Inspection JONATHAN HOM
Rough 8/9/2022 Partial Inspection JONATHAN HOM
Bottom/Toe 8/16/2022 Approved JONATHAN HOM
Final 8/16/2022 Partial Approval JONATHAN HOM
Rough 8/16/2022 Approved JONATHAN HOM
Final 3/1/2023 Permit Finaled AL GAMBLE