1417 N FERMO DR 90272
Certificate Information: 1417 N FERMO DR 90272
- Application / Permit
- 21030-10000-00673
- Plan Check / Job No.
- B21LA01853
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- PROPOSED TO INSTALL OWTS FOR (N) RESIDENCE AND 2 GUEST HOUSE; TOTAL 8 BEDROOMS.: TANK CAPACITY = 7,540 GAL, WITH A SUPPLEMENTAL SYSTEM, PIT 1= 6'DIA. X 21' W/ 5' CAP (16' EFF. DEPTH) PIT 2= 6'DIA. X 36' W/ 9' CAP (27' EFF. DEPTH) PER APPROVED REPORT BY RWQCB, WDR R4-2019-0024 DWQ, GLOBAL ID 100051689. CUT = 117 CY; FILL = 53 CY.; EXPORT = 64 CY.
- Permit Issued
- Issued on 3/31/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/9/2025
Permit Application Status History
| Submitted | 2/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2021 | DAN RYAN EVANGELISTA |
| Corrections Issued | 2/9/2021 | DAN RYAN EVANGELISTA |
| Quality Review Completed | 4/22/2021 | DAN RYAN EVANGELISTA |
| Plan Check Approved | 4/22/2021 | DAN RYAN EVANGELISTA |
| Issued | 3/31/2022 | APPLICANT |
| Permit Finaled | 1/8/2025 | VASIL MIHALEV |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 4/22/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 4/22/2021 | MATTHEW JENKINS |
| Miscellaneous | Cleared | 4/22/2021 | DAN RYAN EVANGELISTA |
Contact Information
| Contractor | Mosser Plumbing & Heating Inc; Lic. No.: 497428-C42 | 13376 BEACH AVENUE MARINA DEL REY, CA 90292 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Poffenbarger,, Kevin Lawrence; Lic. No.: C69089 | 20722 SOUTH MAIN STREET CARSON, CA 90745 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Private Sewage Disposal System | 5/8/2023 | Corrections Issued | RUSSELL BONVOULOIR |
| FLOOD-Proofing Certificate | 6/8/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Rough | 6/8/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Private Sewage Disposal System | 10/5/2023 | Partial Approval | JOHNNY MIRANDA |
| Bottom/Toe | 1/8/2025 | Approved | VASIL MIHALEV |
| FLOOD-Proofing Certificate | 1/8/2025 | Approved | VASIL MIHALEV |
| Final | 1/8/2025 | Permit Finaled | VASIL MIHALEV |
| Rough | 1/8/2025 | Approved | VASIL MIHALEV |