2642 S BRIGHTON AVE 90018
Certificate Information: 2642 S BRIGHTON AVE 90018
- Application / Permit
- 21030-10000-00559
- Plan Check / Job No.
- B21LA01422
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING PERMIT APPLICATION TO 18010-70000-04813 4 UNIT APARTMENT BASED ON RECOMMENDATIONS OF SOILS REPORT
- Permit Issued
- Issued on 6/29/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/17/2023
Permit Application Status History
| Submitted | 3/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | HERNAN ARREOLA |
| Corrections Issued | 4/22/2021 | HERNAN ARREOLA |
| Quality Review Completed | 4/27/2021 | JASON HEALEY |
| Building Plans Picked Up | 5/3/2021 | APPLICANT |
| Plan Check Approved | 6/17/2021 | HERNAN ARREOLA |
| Issued | 6/29/2021 | APPLICANT |
| Permit Finaled | 7/14/2023 | JONATHAN HOM |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Luban Z Construction Corp; Lic. No.: 1033129-B | 5695 SORREL HILLS AVE CHINO HILLS, CA 91709 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 6/28/2023 | Partial Inspection | JONATHAN HOM |
| Final | 6/28/2023 | Corrections Issued | JONATHAN HOM |
| Rough | 6/28/2023 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 7/10/2023 | Partial Inspection | JONATHAN HOM |
| Final | 7/10/2023 | Partial Inspection | JONATHAN HOM |
| Rough | 7/10/2023 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 7/14/2023 | Approved | JONATHAN HOM |
| Final | 7/14/2023 | Permit Finaled | JONATHAN HOM |
| Rough | 7/14/2023 | Approved | JONATHAN HOM |