101 WORLD WAY P1 90045

Certificate Information: 101 WORLD WAY P1 90045

Application / Permit
21026-20000-00048
Plan Check / Job No.
B21VN02011
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(7) Parking Garage
Work Description
**LAX*** REMOVE & REPLACE ENTRY AND EXIT ISLANDS IN PARKING STRUCTURE 1 AND RESTRIPE PARKING
Permit Issued
Issued on 8/23/2021
Issuing Office
Current Status
Permit Finaled on 9/6/2022

Permit Application Status History

Submitted 2/22/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 MARVEL DELACRUZ
Corrections Issued 3/10/2021 MARVEL DELACRUZ
Quality Review Completed 3/16/2021 STEVEN KIM
Building Plans Picked Up 3/17/2021 APPLICANT
Applicant returned to address corrections 5/10/2021 MARVEL DELACRUZ
Applicant returned to address corrections 6/21/2021 MARVEL DELACRUZ
Applicant returned to address corrections 7/16/2021 MARVEL DELACRUZ
Applicant returned to address corrections 8/2/2021 MARVEL DELACRUZ
Applicant returned to address corrections 8/13/2021 MARVEL DELACRUZ
Plan Check Approved 8/16/2021 MARVEL DELACRUZ
Plan Check Approved 8/20/2021 MARVEL DELACRUZ
Issued 8/23/2021 APPLICANT
Permit Finaled 9/1/2022 ALAN NOVAK

Permit Application Clearance Information

Internal circulation Cleared 5/24/2021 KEVIN ARUCAN
Prkng lot landscape/Water mgmt Cleared 5/24/2021 PABLO ESTRADA
Specific Plan Cleared 5/24/2021 KEVIN ARUCAN
City owned building/parcel Cleared 5/25/2021 DANIEL TARICA
Address approval Cleared 6/10/2021 WALLIE JONG
Project Permit Cleared 6/11/2021 VINITA WASKOW
Eng Process Fee Ord 176,300 Cleared 6/28/2021 WALLIE JONG
DAS Clearance Cleared 7/8/2021 MARVEL DELACRUZ
Airport buildings Cleared 7/19/2021 ANDREW KO
Fire Marshal Fire Life Safety Cleared 7/19/2021 ANDREW KO

Contact Information

Contractor B K T Construction Inc; Lic. No.: 787640-B 27788 WEST HANCOCK PKWY      VALENCIA, CA 91355
Engineer Cann,, Merideth Claire; Lic. No.: C57057 334 WALNUT ST      NEWPORT BEACH, CA 92663

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/30/2021 Partial Approval ALAN NOVAK
Excavation/Setback/Form/Re-Bar 8/31/2021 Not Ready for Inspection ALAN NOVAK
Excavation/Setback/Form/Re-Bar 9/1/2021 Approved ALAN NOVAK
Excavation/Setback/Form/Re-Bar 9/22/2021 Partial Approval ALAN NOVAK
Excavation/Setback/Form/Re-Bar 10/5/2021 Approved ALAN NOVAK
Footing/Foundation/Slab 2/18/2022 Partial Approval NICK LAROCCA
Deputy Drilled-In Anchors 3/23/2022 Conditional Approval ALAN NOVAK
Final 8/5/2022 Not Ready for Inspection ALAN NOVAK
Green Building Final 8/5/2022 Approved ALAN NOVAK
SGSOV-Seismic Gas S/O Valve 8/5/2022 SGSOV No Gas ALAN NOVAK
Smoke Detectors 8/5/2022 Approved ALAN NOVAK
Final 9/1/2022 Permit Finaled ALAN NOVAK