3029 S ROBERTSON BLVD 90034

Certificate Information: 3029 S ROBERTSON BLVD 90034

Application / Permit
21026-10000-00264
Plan Check / Job No.
B21LA15463
Group
Building
Type
Nonbldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
RESTRIPE EXISTING PARKING LOT FOR (N) EV CHARGING STATION WITH 10 EV CHARGERS SERVING 18 STALLS AND ASSOCIATED EQUIPMENT
Permit Issued
Issued on 8/8/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 SERGIO GUTIERREZ
Corrections Issued 11/5/2021 SERGIO GUTIERREZ
Quality Review Completed 11/18/2021 FARUK SEZER
Applicant returned to address corrections 1/7/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 2/24/2022 SERGIO GUTIERREZ
Building Plans Picked Up 3/16/2022 APPLICANT
Disabled Access Plans Picked Up 4/14/2022 APPLICANT
Plan Check Approved 8/8/2022 SERGIO GUTIERREZ
Issued 8/8/2022 APPLICANT
CofO in Progress 4/20/2026 FARHAD DADBIN
Permit Finaled 4/22/2026 VASIL MIHALEV
CofO Issued 4/22/2026 VASIL MIHALEV
Permit Finaled 4/22/2026 VASIL MIHALEV

Permit Application Clearance Information

Specific Plan Cleared 7/28/2022 CONNIE CHAUV
DAS Clearance Cleared 8/2/2022 SERGIO GUTIERREZ

Contact Information

Contractor Par Western Line Contractors Llc; Lic. No.: 1084832-A 4770 N BELLEVIEW SUITE 100      KANSAS CITY, MO 64116
Engineer Gorbis,, Stanislav Yevgenyevic; Lic. No.: C81928 1278 CRESCENT TERRACE      SUNNYVALE, CA 94087

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/10/2023 Not Ready for Inspection FARHAD DADBIN
Footing/Foundation/Slab 5/1/2023 Not Ready for Inspection FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 5/10/2023 Partial Approval FARHAD DADBIN
Footing/Foundation/Slab 5/10/2023 Partial Approval FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 6/15/2023 Partial Approval FARHAD DADBIN
Footing/Foundation/Slab 6/15/2023 Partial Approval FARHAD DADBIN
Structural Steel Frame 6/15/2023 Not Ready for Inspection FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 7/11/2023 Partial Approval FARHAD DADBIN
Footing/Foundation/Slab 7/11/2023 Partial Approval FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 7/13/2023 Partial Approval FARHAD DADBIN
Reinforced Concrete Frame 7/13/2023 Partial Approval FARHAD DADBIN
Final 3/25/2026 Corrections Issued FARHAD DADBIN
Final 4/20/2026 OK to Issue CofO FARHAD DADBIN