21909 W VENTURA BLVD 91367
Certificate Information: 21909 W VENTURA BLVD 91367
- Application / Permit
- 21026-10000-00245
- Plan Check / Job No.
- B21LA14935
- Group
- Building
- Type
- Nonbldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- RESTRIPE PARKING SITE WITH PARTIAL SITE IMRROVEMENTS/LANDSCAPE.
- Permit Issued
- Issued on 10/20/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/3/2024
Permit Application Status History
| Submitted | 8/13/2021 | APPLICANT |
| Green Plans Picked Up | 8/24/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 8/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | ARMEN JIVALAGIAN |
| Corrections Issued | 9/14/2021 | ARMEN JIVALAGIAN |
| Quality Review Completed | 9/16/2021 | PETER KIM |
| Building Plans Picked Up | 9/21/2021 | APPLICANT |
| Applicant returned to address corrections | 12/1/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 12/16/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/20/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/21/2022 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 2/11/2022 | ARMEN JIVALAGIAN |
| Plan Check Approved | 8/19/2022 | ARMEN JIVALAGIAN |
| Issued | 10/20/2022 | APPLICANT |
| Permit Finaled | 5/2/2024 | BRIAN KELLY |
Permit Application Clearance Information
| Internal circulation | Cleared | 10/7/2021 | BRANDON WILSON |
| Specific Plan | Cleared | 10/7/2021 | BRANDON WILSON |
| DAS Clearance | Cleared | 1/6/2022 | ARMEN JIVALAGIAN |
| "Q" conditions | Cleared | 1/7/2022 | RICHARD REASER |
| "T" removal | Cleared | 1/7/2022 | RICHARD REASER |
| Miscellaneous | Cleared | 1/7/2022 | RICHARD REASER |
| Prkng lot landscape/Water mgmt | Cleared | 1/7/2022 | RICHARD REASER |
| Specific Plan | Cleared | 1/7/2022 | RICHARD REASER |
| ZA Case | Cleared | 1/7/2022 | RICHARD REASER |
| ZI | Cleared | 1/7/2022 | RICHARD REASER |
| Green Code | Cleared | 7/28/2022 | AARON COSTA |
| Low Impact Development | Cleared | 8/11/2022 | ANDRES COVARRUBIAS |
Contact Information
| Contractor | Grush Ed General Contractor Inc; Lic. No.: 246399-B | 3236 EAST WILLOW STREET SIGNAL HILL, CA 90755 |
| Engineer | Dinari,, Farid; Lic. No.: C38063 | 61 PLYMOUTH IRVINE, CA 92620 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 7/13/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 7/18/2023 | Conditional Approval | BRIAN KELLY |
| Wood Frame | 7/18/2023 | Not Ready for Inspection | BRIAN KELLY |
| Deputy Grading | 7/27/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Grading | 8/10/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 8/11/2023 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 12/5/2023 | Conditional Approval | BRIAN KELLY |
| Final | 5/2/2024 | Permit Finaled | BRIAN KELLY |