424 S COMSTOCK AVE 90024
Certificate Information: 424 S COMSTOCK AVE 90024
- Application / Permit
- 21020-30000-02775
- Plan Check / Job No.
- B21WL05415
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Temop. shoring ***3 of 3 ***
- Permit Issued
- Issued on 6/7/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/9/2025
Permit Application Status History
| Submitted | 12/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | KAVIAN REFAHI |
| Corrections Issued | 12/21/2021 | KAVIAN REFAHI |
| Quality Review Completed | 12/28/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 3/14/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 3/18/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 4/15/2022 | KAVIAN REFAHI |
| Plan Check Approved | 5/9/2022 | KAVIAN REFAHI |
| Issued | 6/7/2022 | APPLICANT |
| Building Plans Picked Up | 6/9/2022 | APPLICANT |
| Permit Finaled | 1/9/2025 | BOBBY KEY |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/14/2022 | KAVIAN REFAHI |
Contact Information
| Architect | , ; Lic. No.: C34496 | 9856 VIDOR DRIVE LOS ANGELES, CA 90035 |
| Contractor | Shore Real Estate Development; Lic. No.: 914609-B | 673 THAYER AVE LOS ANGELES, CA 90024 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 6/15/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 6/17/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Piling/Pier/Caisson | 6/23/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Piling/Pier/Caisson | 6/24/2022 | Corrections Issued | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 6/27/2022 | Approved | MICHAEL PELHAM |
| Piling/Pier/Caisson | 6/28/2022 | Corrections Issued | BRENDAN LOONEY |
| Piling/Pier/Caisson | 6/30/2022 | Partial Approval | BRENDAN LOONEY |
| Final | 1/9/2025 | Permit Finaled | BOBBY KEY |