(N) SITE RETAINING WALLS
Permit Issued
Issued on 6/15/2023
Issuing Office
Metro
Current Status
Permit Finaled on 5/4/2026

Permit Application Status History

Submitted 12/1/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 MARJAN SHENASI
Corrections Issued 12/27/2021 MARJAN SHENASI
Quality Review Completed 1/7/2022 TARIK SAOUD
Applicant returned to address corrections 3/3/2022 MARJAN SHENASI
Applicant returned to address corrections 5/13/2022 YASHAR EMAMI
Applicant returned to address corrections 7/11/2022 YASHAR EMAMI
Applicant returned to address corrections 9/16/2022 YASHAR EMAMI
Plan Check Approved 10/6/2022 YASHAR EMAMI
Building Plans Picked Up 10/6/2022 APPLICANT
Issued 6/15/2023 APPLICANT
Permit Finaled 5/1/2026 JONATHAN HOM

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 3/3/2022 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 4/20/2022 ARMEN SARKISIAN
Eng Process Fee Ord 176,300 Cleared 5/6/2022 AMAAN MALIK
Landscape for retaining wall Cleared 5/9/2022 DALIA MOKAYED

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/18/2023 Approved ROBERT HUGHES
Masonry Wall/Backfill 10/25/2023 Partial Approval ROBERT HUGHES
Masonry Wall/Backfill 10/31/2023 Partial Approval ROBERT HUGHES
Footing/Foundation/Slab 3/14/2024 Partial Approval LANNY MERRICK
Masonry Wall/Backfill 4/2/2024 Partial Approval LANNY MERRICK
Masonry Wall/Backfill 4/19/2024 Partial Approval LANNY MERRICK
Floor/Roof Diaphrgm/Shear Wall 8/27/2024 Not Ready for Inspection LANNY MERRICK
Final 1/29/2026 Corrections Issued JONATHAN HOM
Final 2/5/2026 Corrections Issued JONATHAN HOM
Final 5/1/2026 Permit Finaled JONATHAN HOM