9951 W LIEBE DR 90210

Certificate Information: 9951 W LIEBE DR 90210

Application / Permit
21020-30000-02011
Plan Check / Job No.
B21WL03902
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
NEW FREESTANDING WATER FEATURE WALL ON PILES (8'hX12'10"l)
Permit Issued
Issued on 10/5/2022
Issuing Office
Current Status
Permit Finaled on 11/15/2025

Permit Application Status History

Submitted 9/3/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 ALFREDO JARA
Corrections Issued 9/29/2021 ALFREDO JARA
Quality Review Completed 10/7/2021 TARIK SAOUD
Applicant returned to address corrections 11/22/2021 ALFREDO JARA
Applicant returned to address corrections 1/19/2022 ALFREDO JARA
Applicant returned to address corrections 1/27/2022 ALFREDO JARA
Applicant returned to address corrections 2/1/2022 ALFREDO JARA
Applicant returned to address corrections 2/3/2022 ALFREDO JARA
Applicant returned to address corrections 2/11/2022 ALFREDO JARA
Plan Check Approved 3/10/2022 ALFREDO JARA
Issued 10/5/2022 APPLICANT
Building Plans Picked Up 10/6/2022 APPLICANT
Permit Finaled 11/14/2025 SEAN HAUPT

Permit Application Clearance Information

Watercourse Cleared 10/13/2021 MAHELET GEBEYHU
ZA Case Cleared 10/13/2021 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 12/22/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 3/10/2022 ALFREDO JARA

Contact Information

Contractor A N R Industries Inc; Lic. No.: 692368-B 10537 SANTA MONICA BLVD   STE 240    LOS ANGELES, CA 90025
Engineer Mills,, Garrett Ward; Lic. No.: S5271 553 S OAK KNOLL AVE      PASADENA, CA 91101
Engineer Tsai,, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Gladson,, Richard; Lic. No.: EG1758 1545 VICTORY BL      GLENDALE, CA 91201

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/21/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 11/30/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/14/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/15/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/21/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Light Gage Steel Frame 2/22/2024 Partial Approval SEAN HAUPT
Insulation 6/24/2024 Approved SEAN HAUPT
Special/Order Compliance 6/24/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 7/2/2024 Approved SEAN HAUPT
Final 2/24/2025 Corrections Issued SEAN HAUPT
Final 11/14/2025 Permit Finaled SEAN HAUPT