3000 N GAFFEY ST 90731

Certificate Information: 3000 N GAFFEY ST 90731

Application / Permit
21020-30000-01402
Plan Check / Job No.
B21WL02831
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
New: (9) CIDH Piles and Pile Caps, (2) Equipment Foundation Pile, (3) Spread Footing & Access Platform, Superstructure Platform, Storage Tank Foundation & Containment, Misc. Pipe Supports
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
Permit Finaled on 11/17/2022

Permit Application Status History

Submitted 7/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 DAVID CASTILLO
Corrections Issued 8/2/2021 DAVID CASTILLO
Quality Review Completed 8/19/2021 TARIK SAOUD
Applicant returned to address corrections 11/12/2021 DAVID CASTILLO
Applicant returned to address corrections 11/19/2021 DAVID CASTILLO
Plan Check Approved 11/30/2021 DAVID CASTILLO
Issued 12/2/2021 APPLICANT
Building Plans Picked Up 12/6/2021 APPLICANT
Permit Finaled 11/17/2022 JOEY BUCHANAN

Permit Application Clearance Information

"Q" conditions Cleared 8/31/2021 DENZEL HENDERSON
ZI Cleared 8/31/2021 DENZEL HENDERSON
Metro Rail approval Cleared 9/13/2021 DAVID CASTILLO
Grading Pre-Inspection Cleared 11/12/2021 DAVID CASTILLO

Contact Information

Contractor J M H Engineering And Construction; Lic. No.: 1005643-A 3291 WENDY WAY      LOS ALAMITOS, CA 90720
Engineer Lu,, Xiao Feng; Lic. No.: C82589 2109 MONTEVERDE DR      CHINO HILLS, CA 91709
Engineer Patil,, Uday Keshav; Lic. No.: GE670 4011 P V DRIVE SOUTH      RANCHO PALOS VERDES, CA 90275

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/21/2021 No Access for Inspection JOEY BUCHANAN
Piling/Pier/Caisson 12/21/2021 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 12/21/2021 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 12/28/2021 Partial Approval NICK LAROCCA
Piling/Pier/Caisson 12/28/2021 Partial Approval NICK LAROCCA
Pre-Inspection 12/28/2021 Approved NICK LAROCCA
Deputy Other (see comments) 12/29/2021 Approved NICK LAROCCA
Deputy Reinf. Concrete 12/29/2021 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 1/13/2022 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 1/13/2022 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 1/25/2022 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 1/25/2022 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 2/3/2022 Approved JOEY BUCHANAN
Footing/Foundation/Slab 2/16/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/19/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/20/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/21/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/22/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/23/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/26/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/27/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/28/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/29/2022 Approved JOEY BUCHANAN
Deputy Steel/Welding 9/30/2022 Approved JOEY BUCHANAN
Final 11/17/2022 Permit Finaled JOEY BUCHANAN