419 N VIA DE LA PAZ 90272

Certificate Information: 419 N VIA DE LA PAZ 90272

Application / Permit
21020-30000-01350
Plan Check / Job No.
B21WL02740
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
2 New retaining walls at driveway ramp (Max 10 ft H.T.)
Permit Issued
Issued on 8/23/2022
Issuing Office
Metro
Current Status
Issued on 8/23/2022

Permit Application Status History

Submitted 6/22/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 ALFREDO JARA
Corrections Issued 7/14/2021 ALFREDO JARA
Quality Review Completed 7/29/2021 CHIHARU SUZUKI
Plan Check Approved 8/19/2022 REZA HAGHIGHAT
Building Plans Picked Up 8/22/2022 APPLICANT
Issued 8/23/2022 APPLICANT

Permit Application Clearance Information

Coastal Zone Cleared 5/25/2022 NOAH MCCOY
Landscape for retaining wall Cleared 5/25/2022 NOAH MCCOY
Grading Pre-Inspection Cleared 7/5/2022 ALFREDO JARA
ZA Case Cleared 8/4/2022 SPENCER WEJROWSKI
Excavation more than 5-ft deep Cleared 8/19/2022 CALOSHA APPROVED

Contact Information

Architect Blumenberg,, Richard Leo; Lic. No.: C10862 15200 SUNSET BLVD STE 201      PACIFIC PALISADES, CA 90272
Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

RAMAZANALI ALMASI, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/11/2023 Not Ready for Inspection VASIL MIHALEV
Pre-Inspection 5/11/2023 Not Ready for Inspection VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 5/12/2023 Approved VASIL MIHALEV
Pre-Inspection 5/12/2023 Approved VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 5/18/2023 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 5/19/2023 Approved VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 5/25/2023 Conditional Approval RUSSELL BONVOULOIR
Pre-Inspection 5/25/2023 Conditional Approval RUSSELL BONVOULOIR
Reinforced Concrete Frame 5/25/2023 Conditional Approval RUSSELL BONVOULOIR
Pre-Inspection 6/6/2023 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 6/9/2023 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 6/9/2023 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Masonry 6/21/2023 Conditional Approval RUSSELL BONVOULOIR
Masonry Wall/Backfill 6/22/2023 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 6/23/2023 Partial Approval RUSSELL BONVOULOIR
Masonry Wall/Backfill 6/23/2023 Partial Approval RUSSELL BONVOULOIR
Pre-Inspection 6/23/2023 Partial Approval RUSSELL BONVOULOIR
Pre-Inspection 7/7/2023 Partial Approval MATTHEW JENKINS