950 N MORAGA DR 90049

Certificate Information: 950 N MORAGA DR 90049

Application / Permit
21020-30000-01290
Plan Check / Job No.
B21WL02626
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
new retaining walls
Permit Issued
Issued on 5/10/2022
Issuing Office
Current Status
Permit Finaled on 6/3/2026

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 TARIK SAOUD
Corrections Issued 7/4/2021 TARIK SAOUD
Quality Review Completed 7/8/2021 CHIHARU SUZUKI
Plans on Hold 12/2/2021 TARIK SAOUD
Hold Released 2/4/2022 TARIK SAOUD
Plans on Hold 2/4/2022 TARIK SAOUD
Hold Released 2/9/2022 CHIHARU SUZUKI
Plans on Hold 2/24/2022 CHIHARU SUZUKI
Hold Released 4/5/2022 CHIHARU SUZUKI
Plans on Hold 4/28/2022 CHIHARU SUZUKI
Hold Released 5/10/2022 CHIHARU SUZUKI
Plan Check Approved 5/10/2022 CHIHARU SUZUKI
Issued 5/10/2022 APPLICANT
Building Plans Picked Up 5/11/2022 APPLICANT
Permit Finaled 6/2/2026 EVAN COOPER

Permit Application Clearance Information

Landscape for retaining wall Cleared 10/27/2021 DANG NGUYEN
Low Impact Development Cleared 1/13/2022 ORVAL HERNANDEZ-MARCI

Contact Information

Contractor Owner-Builder       ,
Engineer Yazdan,, Fred Faramarz; Lic. No.: C35704 58 FEATHER RIDGE      MISSION VIEJO, CA 92692

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/5/2022 Approved CARLOS MATAMOROS
Deputy Reinf. Concrete 7/7/2022 Approved JONATHAN HOM
Excavation/Setback/Form/Re-Bar 7/29/2022 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 7/29/2022 Not Ready for Inspection CHARLES POWELL
Piling/Pier/Caisson 7/29/2022 Not Ready for Inspection CHARLES POWELL
Special/Order Compliance 7/29/2022 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 8/12/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 8/12/2022 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 8/12/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/16/2022 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/5/2022 Not Ready for Inspection CARLOS MATAMOROS
Reinforced Concrete Frame 10/21/2022 Partial Approval CARLOS MATAMOROS
Reinforced Masonry Frame 10/21/2022 Partial Approval CARLOS MATAMOROS
Reinforced Concrete Frame 12/5/2022 Not Ready for Inspection CARLOS MATAMOROS
Piling/Pier/Caisson 2/10/2023 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 4/5/2023 Conditional Approval MICHAEL PELHAM
Piling/Pier/Caisson 4/6/2023 Partial Approval CARLOS MATAMOROS
Reinforced Concrete Frame 4/6/2023 Partial Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 6/16/2023 Conditional Approval CARLOS MATAMOROS
Piling/Pier/Caisson 8/10/2023 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 9/11/2023 Partial Approval CARLOS MATAMOROS
Final 6/2/2026 Permit Finaled EVAN COOPER