10107 W ROSSBURY PL 90064
Certificate Information: 10107 W ROSSBURY PL 90064
- Application / Permit
- 21020-30000-00539
- Plan Check / Job No.
- B21WL00821
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Shoring for (N) 2-Story S.F.D w/Basement and Attached Garage
- Permit Issued
- Issued on 8/25/2021
- Issuing Office
- Current Status
- Permit Finaled on 5/3/2024
Permit Application Status History
| Submitted | 2/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2021 | DAVID CASTILLO |
| Corrections Issued | 3/25/2021 | DAVID CASTILLO |
| Quality Review Completed | 3/31/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 5/12/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 5/25/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/22/2021 | DAVID CASTILLO |
| Plan Check Approved | 8/24/2021 | DAVID CASTILLO |
| Issued | 8/25/2021 | APPLICANT |
| Building Plans Picked Up | 8/26/2021 | APPLICANT |
| Permit Finaled | 5/2/2024 | OGANES TARAKHCHYAN |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 4/12/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2021 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 5/20/2021 | DAVID CASTILLO |
Contact Information
| Architect | 9856, Vidor Drive; Lic. No.: C34496 | LOS ANGELES, CA 90035 |
| Contractor | Owner-Builder | , |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Ganeshwara,, Vela; Lic. No.: GE2736 | 19420 KILFINAN ST PORTER RANCH, CA 91326 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/4/2021 | Partial Inspection | KENNETH NAGLE |
| Deputy Grading | 10/7/2021 | Conditional Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 10/13/2021 | Partial Approval | KEVIN SARGSYAN |
| Structural Steel Frame | 10/13/2021 | Partial Approval | KEVIN SARGSYAN |
| Final | 10/26/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Final | 10/26/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Final | 5/2/2024 | Permit Finaled | OGANES TARAKHCHYAN |
| Green Building Final | 5/2/2024 | Approved | OGANES TARAKHCHYAN |