13201 W ROSE AVE 90066
Certificate Information: 13201 W ROSE AVE 90066
- Application / Permit
- 21020-30000-00479
- Plan Check / Job No.
- B21WL01065
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- new retaining wall
- Permit Issued
- Issued on 9/28/2021
- Issuing Office
- Current Status
- Issued on 9/28/2021
Permit Application Status History
| Submitted | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2021 | TARIK SAOUD |
| Corrections Issued | 3/23/2021 | TARIK SAOUD |
| Quality Review Completed | 3/31/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/9/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 8/25/2021 | TARIK SAOUD |
| Plan Check Approved | 9/21/2021 | TARIK SAOUD |
| Issued | 9/28/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2021 | SAUL GARCIA |
| Work Adjacent to Public Way | Cleared | 6/28/2021 | SAUL GARCIA |
| Low Impact Development | Cleared | 7/29/2021 | TA ANH |
| Excavation more than 5-ft deep | Cleared | 9/15/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 9/15/2021 | TARIK SAOUD |
| Miscellaneous | Cleared | 9/15/2021 | TARIK SAOUD |
Contact Information
| Architect | Winters,, Patrick Charles; Lic. No.: C22032 | 11410 BIONA DRIVE LOS ANGELES, CA 90066 |
| Contractor | Westside Construction; Lic. No.: 852976-B | 1531 15TH STREET APT 6 SANTA MONICA, CA 90404 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Varela, Olivas, Benjamin; Lic. No.: S5714 | 6007 WASHINGTON BLVD CULVER CITY, CA 90232 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/13/2021 | Approved | AL GAMBLE |
| Pre-Inspection | 2/15/2022 | Partial Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 2/18/2022 | Conditional Approval | JONATHAN HOM |
| Excavation/Setback/Form/Re-Bar | 3/3/2022 | Partial Approval | AL GAMBLE |
| Deputy Reinf. Concrete | 3/4/2022 | Approved | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Partial Approval | AL GAMBLE |
| Reinforced Concrete Frame | 3/24/2022 | Approved | AL GAMBLE |
| Deputy Shotcrete | 3/25/2022 | Approved | AL GAMBLE |
| Deputy Drilled-In Anchors | 4/25/2022 | Conditional Approval | AL GAMBLE |
| Footing/Foundation/Slab | 4/25/2022 | Corrections Issued | AL GAMBLE |
| Deputy Reinf. Concrete | 4/26/2022 | Conditional Approval | AL GAMBLE |
| Footing/Foundation/Slab | 4/27/2022 | Partial Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 5/5/2022 | Partial Approval | AL GAMBLE |
| Reinforced Concrete Frame | 5/5/2022 | Partial Approval | AL GAMBLE |
| Deputy Shotcrete | 5/11/2022 | Approved | JONATHAN HOM |
| Deputy Drilled-In Anchors | 5/24/2022 | Approved | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Partial Approval | AL GAMBLE |
| Final | 4/21/2023 | Partial Inspection | MATTHEW JENKINS |