3545 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3545 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 21020-30000-00120
- Plan Check / Job No.
- B21WL00288
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- New Retaining Walls
- Permit Issued
- Issued on 8/24/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/23/2022
Permit Application Status History
| Submitted | 1/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | DAVID CASTILLO |
| Corrections Issued | 2/1/2021 | DAVID CASTILLO |
| Quality Review Completed | 2/8/2021 | TARIK SAOUD |
| Building Plans Picked Up | 2/9/2021 | APPLICANT |
| Applicant returned to address corrections | 5/5/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 6/22/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/7/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/3/2021 | DAVID CASTILLO |
| Plan Check Approved | 8/12/2021 | DAVID CASTILLO |
| Issued | 8/24/2021 | APPLICANT |
| Permit Finaled | 6/22/2022 | AL GAMBLE |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 5/12/2021 | MINDY NGUYEN |
| Excavation more than 5-ft deep | Cleared | 6/22/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 6/22/2021 | DAVID CASTILLO |
Contact Information
| Contractor | Decardo'S Pools And Landscape Inc; Lic. No.: 532429-C53 | 23705 VANOWEN ST #114 WEST HILLS, CA 91307 |
| Engineer | Azarmy,, Cyrus; Lic. No.: L9404 | 4402 CHARLEMONT AVE WOODLAND HILLS, CA 91364 |
| Engineer | Franceschi,, Paul; Lic. No.: S4309 | 2388 KENILWORTH AVE LOS ANGELES, CA 90039 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/23/2021 | Not Ready for Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 11/23/2021 | Partial Approval | AL GAMBLE |
| Footing/Foundation/Slab | 11/23/2021 | Partial Approval | AL GAMBLE |
| Deputy Reinf. Concrete | 11/24/2021 | Approved | AL GAMBLE |
| Masonry Wall/Backfill | 12/1/2021 | Partial Approval | AL GAMBLE |
| Footing/Foundation/Slab | 12/10/2021 | Partial Approval | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 12/15/2021 | Not Ready for Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 12/20/2021 | Partial Approval | AL GAMBLE |
| Deputy Reinf. Masonry | 1/5/2022 | No Access for Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 1/7/2022 | Partial Approval | AL GAMBLE |
| Deputy Reinf. Masonry | 1/10/2022 | No Access for Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 1/20/2022 | Partial Approval | AL GAMBLE |
| Footing/Foundation/Slab | 1/20/2022 | Partial Approval | AL GAMBLE |
| Deputy Reinf. Masonry | 1/25/2022 | No Access for Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 1/25/2022 | No Access for Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 1/27/2022 | Partial Approval | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 2/1/2022 | Partial Approval | AL GAMBLE |
| Footing/Foundation/Slab | 2/1/2022 | Partial Approval | AL GAMBLE |
| Masonry Wall/Backfill | 2/1/2022 | Partial Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 2/3/2022 | Approved | VASIL MIHALEV |
| Footing/Foundation/Slab | 2/3/2022 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 2/8/2022 | Partial Inspection | JONATHAN HOM |
| Deputy Reinf. Masonry | 2/10/2022 | No Access for Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 2/11/2022 | Not Ready for Inspection | AL GAMBLE |
| Final | 6/22/2022 | Permit Finaled | AL GAMBLE |