1844 N ALEXANDRIA AVE 90027
Certificate Information: 1844 N ALEXANDRIA AVE 90027
- Application / Permit
- 21020-30000-00077
- Plan Check / Job No.
- B20WL05354
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Retaining Wall
- Work Description
- New retaining wall
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/25/2023
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | MARJAN SHENASI |
| Corrections Issued | 1/11/2021 | MARJAN SHENASI |
| Quality Review Completed | 1/20/2021 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/29/2021 | APPLICANT |
| Application Withdrawn-Void | 6/9/2021 | CHIHARU SUZUKI |
| Re-Activate Application | 6/10/2021 | MARJAN SHENASI |
| Plan Check Approved | 8/19/2021 | MARJAN SHENASI |
| Issued | 8/25/2022 | APPLICANT |
| Permit Finaled | 10/24/2023 | RONALD JIMENEZ |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/5/2021 | LOUIS ORTEGA |
| GPI Written Notices | Cleared | 3/12/2021 | MARJAN SHENASI |
| Grading Pre-Inspection | Cleared | 3/12/2021 | MARJAN SHENASI |
Contact Information
| Architect | Maly,, Farzin; Lic. No.: C33731 | 7136 HASKELL AVENUE # 320 VAN NUYS, CA 91406 |
| Contractor | A & R Builders Inc; Lic. No.: 1079436-B | 500 N CENTRAL AVE #600 GLENDALE, CA 91203 |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/27/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 8/2/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 8/7/2023 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall/Backfill | 8/22/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Masonry Wall/Backfill | 8/24/2023 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 8/31/2023 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall/Backfill | 9/8/2023 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 9/20/2023 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 10/11/2023 | Partial Approval | JEROME BLACKWOOD |
| Masonry Wall/Backfill | 10/18/2023 | Approved | RONALD JIMENEZ |
| Final | 10/24/2023 | Permit Finaled | RONALD JIMENEZ |