100 S LORING AVE 90024
Certificate Information: 100 S LORING AVE 90024
- Application / Permit
- 21020-20002-00245
- Plan Check / Job No.
- B21VN13795
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW 5'-4" X 6' MAIL BOX PER ZA-2021-2890-F. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/17/2022
- Issuing Office
- Current Status
- Permit Finaled on 2/2/2023
Permit Application Status History
| Submitted | 10/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2021 | RAPHAEL ROSAS |
| Corrections Issued | 10/17/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/26/2021 | RAPHAEL ROSAS |
| Issued | 1/17/2022 | APPLICANT |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| Permit Finaled | 2/1/2023 | CARLOS MATAMOROS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/28/2021 | ANTHONY MAINEZ |
| Work Adjacent to Public Way | Cleared | 10/28/2021 | ANTHONY MAINEZ |
| ZA Case | Cleared | 12/10/2021 | LAUREN PADICK |
| ZA Case | Cleared | 12/10/2021 | LAUREN PADICK |
| ZA Case | Cleared | 12/10/2021 | LAUREN PADICK |
| ZA Case | Cleared | 12/14/2021 | LAUREN PADICK |
| Grading Pre-Inspection | Cleared | 12/20/2021 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2022 | DINAH GARIN |
Contact Information
| Architect | Brouse,, Jon Robert; Lic. No.: C22200 | 12930 VENTURA BLVD SUITE 214 STUDIO CITY, CA 91604 |
| Contractor | Mercier W J Construction Inc; Lic. No.: 792497-B | 2758 BRIARPATCH DR SIMI VALLEY, CA 93065 |
| Engineer | Mercado,, Lizandro; Lic. No.: S4331 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/21/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 1/25/2022 | Corrections Issued | BRENDAN LOONEY |
| Wood Frame | 3/31/2022 | Approved | BRENDAN LOONEY |
| Final | 7/22/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 1/26/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 2/1/2023 | Permit Finaled | CARLOS MATAMOROS |