14929 W CORONA DEL MAR 90272
Certificate Information: 14929 W CORONA DEL MAR 90272
- Application / Permit
- 21020-20001-01438
- Plan Check / Job No.
- B22VN05159
- Group
- Building
- Type
- Nonbldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- SUPP TO PERMIT 21020-20000-01438 TO ADD 168' LF RET. WALL (RET. WALL #2; MAX HEIGHT: 3'-3")
- Permit Issued
- Issued on 5/26/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/12/2023
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | SEAN SHAHMIRI |
| Corrections Issued | 5/2/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 5/2/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| Applicant returned to address corrections | 5/19/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 5/26/2022 | SEAN SHAHMIRI |
| Issued | 5/26/2022 | APPLICANT |
| Permit Finaled | 10/11/2023 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Coastal Zone | Cleared | 5/24/2022 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 5/24/2022 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 5/24/2022 | LOUIS ORTEGA |
Contact Information
| Architect | Azadi,, Bijan; Lic. No.: C18972 | 2825 PLAZA DEL AMO # 179 TORRANCE, CA 90503 |
| Contractor | A T H Construction; Lic. No.: 691539-B | 18160 CHASE STREET NORTHRIDGE, CA 91325 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/9/2022 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/10/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 6/13/2022 | Partial Inspection | TIMOTHY POWELL |
| Deputy Reinf. Concrete | 6/17/2022 | Corrections Issued | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 6/22/2022 | Partial Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 7/1/2022 | Partial Inspection | JONATHAN HOM |
| Masonry Wall/Backfill | 7/7/2022 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall/Backfill | 7/6/2023 | Partial Inspection | MATTHEW JENKINS |
| Final | 10/11/2023 | Permit Finaled | JOHNNY MIRANDA |