16661 W ADLON ROAD 91436

Certificate Information: 16661 W ADLON ROAD 91436

Application / Permit
21020-20000-02476
Plan Check / Job No.
B21VN14992
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW RETAINING WALLS 6'8" FT HIGH X 40'9" LF LONG ( 6 FT MAX ABOVE NATURAL GRADE IN THE REQUIRED SIDE YARD), NEW 6 FT HIGH X 51'3" BLOCK WALL , ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/1/2024
Issuing Office
Valley
Current Status
Issued on 11/1/2024

Permit Application Status History

Submitted 11/1/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 RARES BODEA
Corrections Issued 11/24/2021 RARES BODEA
Quality Review Completed 12/2/2021 STEVEN KIM
Building Plans Picked Up 12/6/2021 APPLICANT
Applicant returned to address corrections 6/8/2022 RARES BODEA
Applicant returned to address corrections 9/21/2022 RARES BODEA
Plan Check Approved 12/15/2022 RARES BODEA
Issued 11/1/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/4/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 8/11/2022 RIDWAN HARDY
Construction within easement Cleared 8/11/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/21/2022 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 12/15/2022 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/19/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 12/30/2024 Not Ready for Inspection THOMAS FINNILA
Deputy Reinf. Concrete 3/3/2025 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 3/3/2025 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 3/12/2025 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 3/13/2025 Not Ready for Inspection THOMAS FINNILA
Deputy Reinf. Concrete 3/17/2025 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 9/3/2025 No Access for Inspection MANUEL TEJADA
Footing/Foundation/Slab 9/3/2025 Partial Approval MANUEL TEJADA
Deputy Reinf. Concrete 9/4/2025 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 9/22/2025 Corrections Issued MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 9/26/2025 Partial Approval MANUEL TEJADA
Deputy Reinf. Concrete 10/3/2025 Approved MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 10/27/2025 Corrections Issued CHARLES POWELL
Excavation/Setback/Form/Re-Bar 11/3/2025 Partial Inspection ALEXANDER HELFER
Deputy Reinf. Concrete 11/25/2025 Conditional Approval ALEXANDER HELFER
Excavation/Setback/Form/Re-Bar 12/2/2025 Conditional Approval ROBERT PINA
Deputy Reinf. Concrete 12/3/2025 No Access for Inspection MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 1/21/2026 Partial Approval MANUEL TEJADA