12700 W WOODGREEN ST 90066

Certificate Information: 12700 W WOODGREEN ST 90066

Application / Permit
21020-20000-02330
Plan Check / Job No.
B21VN13955
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW SITE RETAINING WALL WITH SHORING , L=170'-9"
Permit Issued
Issued on 8/25/2022
Issuing Office
Metro
Current Status
Permit Finaled on 7/18/2024

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 ARTIN ZARUKIAN
Corrections Issued 10/25/2021 ARTIN ZARUKIAN
Quality Review Completed 10/28/2021 STEVEN KIM
Building Plans Picked Up 11/1/2021 APPLICANT
Plan Check Approved 4/13/2022 ARTIN ZARUKIAN
Issued 8/25/2022 APPLICANT
Permit Finaled 7/11/2024 MATTHEW JENKINS

Permit Application Clearance Information

Miscellaneous Cleared 10/27/2021 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 1/4/2022 DINAH GARIN
Excavation more than 5-ft deep Cleared 4/5/2022 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 4/8/2022 SAUL GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/13/2022 Approved AL GAMBLE
Excavation/Setback/Form/Re-Bar 10/13/2022 Partial Inspection AL GAMBLE
Deputy Reinf. Concrete 10/17/2022 Approved AL GAMBLE
Piling/Pier/Caisson 10/17/2022 Partial Inspection AL GAMBLE
Excavation/Setback/Form/Re-Bar 11/15/2022 Not Ready for Inspection AL GAMBLE
Excavation/Setback/Form/Re-Bar 11/17/2022 Partial Approval AL GAMBLE
Deputy Drilled-In Anchors 11/18/2022 No Access for Inspection AL GAMBLE
Excavation/Setback/Form/Re-Bar 11/23/2022 Not Ready for Inspection AL GAMBLE
Footing/Foundation/Slab 11/30/2022 Partial Approval AL GAMBLE
Deputy Shotcrete 12/5/2022 Partial Approval AL GAMBLE
Deputy Drilled-In Anchors 12/15/2022 No Access for Inspection AL GAMBLE
Footing/Foundation/Slab 12/20/2022 Partial Approval MATTHEW JENKINS
Footing/Foundation/Slab 12/27/2022 Partial Approval JONATHAN HOM
Deputy Shotcrete 1/3/2023 Conditional Approval MATTHEW JENKINS
Deputy Drilled-In Anchors 1/4/2023 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 1/18/2023 Partial Approval MATTHEW JENKINS
Footing/Foundation/Slab 1/25/2023 Partial Inspection MATTHEW JENKINS
Deputy Reinf. Concrete 1/27/2023 Conditional Approval MATTHEW JENKINS
Footing/Foundation/Slab 1/30/2023 Not Ready for Inspection MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 2/1/2023 Not Ready for Inspection AL GAMBLE
Excavation/Setback/Form/Re-Bar 2/3/2023 Partial Approval MATTHEW JENKINS
Deputy Shotcrete 2/6/2023 Conditional Approval RUSSELL BONVOULOIR
Final 7/11/2024 Permit Finaled MATTHEW JENKINS