4000 N BALLINA DR 91436

Certificate Information: 4000 N BALLINA DR 91436

Application / Permit
21020-20000-02296
Plan Check / Job No.
B21VN13762
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
2 NEW RETAINING WALLS ON PILES [RET. WALL 1 L: 34'-6" MAX HT: 10'] [RET. WALL 2 L: 175' MAX HT: 10']
Permit Issued
Issued on 3/17/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 1/27/2026

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 SEAN SHAHMIRI
Corrections Issued 10/24/2021 SEAN SHAHMIRI
Quality Review Completed 10/26/2021 OMID HEDAYAT
Building Plans Picked Up 11/1/2021 APPLICANT
Applicant returned to address corrections 4/12/2022 SEAN SHAHMIRI
Applicant returned to address corrections 5/6/2022 SEAN SHAHMIRI
Plan Check Approved 8/9/2022 SEAN SHAHMIRI
Issued 3/17/2023 APPLICANT
Permit Finaled 1/27/2026 ROBERT PINA

Permit Application Clearance Information

Construction near power lines Cleared 11/22/2021 WALTER RAMIREZ
Landscape for retaining wall Cleared 2/18/2022 MIGUEL GAMBOA

Contact Information

Contractor Sperling Group Inc; Lic. No.: 1061452-B 11769 CHENAULT STREET      LOS ANGELES, CA 90049
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/22/2023 Approved ROBERT PINA
Piling/Pier/Caisson 6/7/2023 Partial Approval ROBERT PINA
Deputy Reinf. Concrete 6/8/2023 Approved ROBERT PINA
Excavation/Setback/Form/Re-Bar 9/6/2023 Partial Approval ROBERT PINA
Excavation/Setback/Form/Re-Bar 9/22/2023 Approved ROBERT PINA
Footing/Foundation/Slab 9/22/2023 Partial Approval ROBERT PINA
Excavation/Setback/Form/Re-Bar 10/23/2023 Partial Approval ROBERT PINA
Excavation/Setback/Form/Re-Bar 3/19/2024 Approved ROBERT PINA
Excavation/Setback/Form/Re-Bar 4/3/2024 Partial Approval ROBERT PINA
Excavation/Setback/Form/Re-Bar 4/25/2024 Approved ROBERT PINA
Excavation/Setback/Form/Re-Bar 12/17/2025 Not Ready for Inspection MANUEL TEJADA
Final 1/27/2026 Permit Finaled ROBERT PINA