675 N MUSKINGUM AVE 90272

Certificate Information: 675 N MUSKINGUM AVE 90272

Application / Permit
21020-20000-01690
Plan Check / Job No.
B21VN10062
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
ONE NEW RETAINING WALL ( L =140'-0", H= 10'-0" )
Permit Issued
Issued on 9/7/2022
Issuing Office
Valley
Current Status
Permit Finaled on 6/25/2024

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 MOHAMMAD ESMAILI
Corrections Issued 9/10/2021 MOHAMMAD ESMAILI
Quality Review Completed 9/10/2021 OMID HEDAYAT
Building Plans Picked Up 9/14/2021 APPLICANT
Applicant returned to address corrections 5/28/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/10/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/15/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/17/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/19/2022 MOHAMMAD ESMAILI
Plan Check Approved 8/25/2022 MOHAMMAD ESMAILI
Issued 9/7/2022 APPLICANT
Permit Finaled 6/25/2024 JOHNNY MIRANDA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/10/2021 DINAH GARIN
GPI Written Notices Cleared 2/7/2022 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 2/7/2022 MOHAMMAD ESMAILI
Roof/Waste drainage to street Cleared 5/5/2022 DINAH GARIN
Excavation more than 5-ft deep Cleared 8/31/2022 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

RAMAZANALI ALMASI, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2022 Partial Approval TIMOTHY POWELL
Piling/Pier/Caisson 9/26/2022 Partial Approval TIMOTHY POWELL
Piling/Pier/Caisson 12/6/2022 Partial Inspection JONATHAN HOM
Piling/Pier/Caisson 12/9/2022 Not Ready for Inspection TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 4/11/2023 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 4/19/2023 Partial Approval RUSSELL BONVOULOIR
Deputy Shotcrete 5/5/2023 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 5/5/2023 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 5/5/2023 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 5/9/2023 Partial Inspection RUSSELL BONVOULOIR
Final 4/2/2024 Corrections Issued JOHNNY MIRANDA
Final 4/10/2024 Not Ready for Inspection JOHNNY MIRANDA
Final 4/25/2024 Not Ready for Inspection JOHNNY MIRANDA
Final 6/11/2024 Not Ready for Inspection AL GAMBLE
Special/Order Compliance 6/13/2024 Partial Inspection JOHNNY MIRANDA
Final 6/14/2024 Not Ready for Inspection JOHNNY MIRANDA
Special/Order Compliance 6/17/2024 Not Ready for Inspection MATTHEW JENKINS
Final 6/25/2024 Permit Finaled JOHNNY MIRANDA