5326 N DONNA AVE 91356

Certificate Information: 5326 N DONNA AVE 91356

Application / Permit
21020-20000-01579
Plan Check / Job No.
B21VN09255
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW RETAINING/FENCE WALL (MAX HEIGHT= 6'-0" [3' AT FRONT YARD], TOTAL LENGTH= 602.66')
Permit Issued
Issued on 10/21/2021
Issuing Office
Current Status
Permit Finaled on 3/4/2022

Permit Application Status History

Submitted 7/15/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 SEAN SHAHMIRI
Corrections Issued 8/25/2021 SEAN SHAHMIRI
Quality Review Completed 8/31/2021 OMID HEDAYAT
Building Plans Picked Up 9/1/2021 APPLICANT
Applicant returned to address corrections 10/21/2021 SEAN SHAHMIRI
Plan Check Approved 10/21/2021 SEAN SHAHMIRI
Issued 10/21/2021 APPLICANT
Permit Finaled 3/3/2022 ALEXANDER HELFER

Permit Application Clearance Information

Landscape for retaining wall Cleared 10/12/2021 STEVEN WECHSLER

Contact Information

Contractor Lightning Construction & Design Inc; Lic. No.: 951122-B 6047 TAMPA AVE #303      TARZANA, CA 91356
Engineer Haro,, Ruben; Lic. No.: GE2990 555 N LANTANA ST STE 492      CAMARILLO, CA 93010
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/6/2021 Corrections Issued ALEXANDER ANDREWS
Excavation/Setback/Form/Re-Bar 12/10/2021 Corrections Issued TIMOTHY POWELL
Footing/Foundation/Slab 12/10/2021 Partial Approval TIMOTHY POWELL
Masonry Wall/Backfill 12/22/2021 Partial Approval ALEXANDER ANDREWS
Excavation/Setback/Form/Re-Bar 1/20/2022 Partial Approval ALEXANDER ANDREWS
Footing/Foundation/Slab 1/27/2022 Partial Approval ALEXANDER ANDREWS
Final 3/3/2022 Permit Finaled ALEXANDER HELFER