11749 N AINSLEY CT 91326
Certificate Information: 11749 N AINSLEY CT 91326
- Application / Permit
- 21020-20000-01466
- Plan Check / Job No.
- B21VN08664
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Fence Wall
- Work Description
- (N) 6' HIGH FENCE/RETAINING WALL (ALONG BOTH SIDE PROPRTY LINE). (82'-9" & 79'-9"LF)(PROTO WALL II_PER LA STANDARD PLAN #520)SEE COMMENTS.
- Permit Issued
- Issued on 12/27/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/15/2022
Permit Application Status History
| Submitted | 7/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2021 | SERGIO MUNIZ |
| Corrections Issued | 7/10/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 9/25/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/19/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 11/30/2021 | SERGIO MUNIZ |
| Plan Check Approved | 12/22/2021 | SERGIO MUNIZ |
| Issued | 12/27/2021 | APPLICANT |
| Building Plans Picked Up | 1/20/2022 | APPLICANT |
| Permit Finaled | 3/14/2022 | SEAN WIRCH |
Permit Application Clearance Information
| "T" removal | Cleared | 8/26/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 8/26/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 8/26/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 8/26/2021 | DANG NGUYEN |
| ZA Case | Cleared | 8/26/2021 | DANG NGUYEN |
| ZA Case | Cleared | 8/26/2021 | DANG NGUYEN |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
| Engineer | Majeroni,, Todd Edward; Lic. No.: C69616 | 9080 W CHEYENNE AVE STE 120 LAS VEGAS, NV 89129 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/9/2022 | Approved | SEAN WIRCH |
| Deputy Drilled-In Anchors | 2/25/2022 | Approved | SEAN WIRCH |
| Final | 3/14/2022 | Permit Finaled | SEAN WIRCH |