592 N BEVERLY GLEN BLVD 90077
Certificate Information: 592 N BEVERLY GLEN BLVD 90077
- Application / Permit
- 21020-20000-01401
- Plan Check / Job No.
- B21VN06040
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- ONE (N) RETAINING WALL [H=5.5' MAX RETAINING, L=163'] ON NORTH SIDE OF PROPERTY AND (1) PORTION OF THE WALL ON NORTH SIDE [H= MAX 2.5', L=30'] ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- Issued on 1/28/2022
Permit Application Status History
| Submitted | 5/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 6/24/2021 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 6/29/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/2/2021 | APPLICANT |
| Applicant returned to address corrections | 10/14/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 10/25/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 10/28/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 1/11/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 1/13/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/28/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 10/8/2021 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 10/25/2021 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Warner Douglas Wade; Lic. No.: 497676-B | 726 CALLE CARDO THOUSAND OAKS, CA 91360 |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/26/2022 | Partial Approval | JONATHAN HOM |
| Footing/Foundation/Slab | 6/7/2023 | Approved | VASIL MIHALEV |
| Reinforced Masonry Frame | 6/29/2023 | Partial Approval | CHARLES POWELL |
| Masonry Wall/Backfill | 7/13/2023 | Partial Approval | CHARLES POWELL |