5032 N DON PIO DR 91364
Certificate Information: 5032 N DON PIO DR 91364
- Application / Permit
- 21020-20000-01286
- Plan Check / Job No.
- B21VN07582
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW 10'-0" HIGH RETAINING WALL ON PILES AT REAR OF PROPERTY
- Permit Issued
- Issued on 7/6/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/2/2023
Permit Application Status History
| Submitted | 6/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | PETER MOSESIAN |
| Corrections Issued | 8/1/2021 | PETER MOSESIAN |
| Quality Review Completed | 8/18/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/20/2021 | APPLICANT |
| Plan Check Approved | 7/6/2022 | PETER MOSESIAN |
| Issued | 7/6/2022 | APPLICANT |
| Permit Finaled | 10/2/2023 | ROBERT PINA |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/13/2021 | WALTER RAMIREZ |
| Landscape for retaining wall | Cleared | 6/22/2022 | MIGUEL GAMBOA |
Contact Information
| Architect | Bagheri-Fard,, Karim; Lic. No.: C29280 | 4516 SAN TAELA COURT WOODLAND HILLS, CA 91364 |
| Contractor | Owner-Builder | , |
| Engineer | Kamboj,, Naresh Chander; Lic. No.: C21893 | 7838 QUIMBY AVE CANOGA PARK, CA 91304 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 9/20/2022 | Partial Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 9/21/2022 | No Access for Inspection | PETER FOLLING |
| Structural Steel Frame | 10/4/2022 | Approved | VASIL MIHALEV |
| Deputy Shotcrete | 12/6/2022 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 5/25/2023 | Not Ready for Inspection | ROBERT PINA |
| Footing/Foundation/Slab | 5/26/2023 | Partial Approval | ROBERT PINA |
| Reinforced Concrete Frame | 6/5/2023 | Partial Approval | ROBERT PINA |
| Final | 10/2/2023 | Permit Finaled | ROBERT PINA |