5032 N DON PIO DR 91364

Certificate Information: 5032 N DON PIO DR 91364

Application / Permit
21020-20000-01286
Plan Check / Job No.
B21VN07582
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW 10'-0" HIGH RETAINING WALL ON PILES AT REAR OF PROPERTY
Permit Issued
Issued on 7/6/2022
Issuing Office
Current Status
Permit Finaled on 10/2/2023

Permit Application Status History

Submitted 6/25/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 PETER MOSESIAN
Corrections Issued 8/1/2021 PETER MOSESIAN
Quality Review Completed 8/18/2021 OMID HEDAYAT
Building Plans Picked Up 8/20/2021 APPLICANT
Plan Check Approved 7/6/2022 PETER MOSESIAN
Issued 7/6/2022 APPLICANT
Permit Finaled 10/2/2023 ROBERT PINA

Permit Application Clearance Information

Construction near power lines Cleared 9/13/2021 WALTER RAMIREZ
Landscape for retaining wall Cleared 6/22/2022 MIGUEL GAMBOA

Contact Information

Architect Bagheri-Fard,, Karim; Lic. No.: C29280 4516 SAN TAELA COURT      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,
Engineer Kamboj,, Naresh Chander; Lic. No.: C21893 7838 QUIMBY AVE      CANOGA PARK, CA 91304
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 9/20/2022 Partial Approval LANNY MERRICK
Deputy Reinf. Concrete 9/21/2022 No Access for Inspection PETER FOLLING
Structural Steel Frame 10/4/2022 Approved VASIL MIHALEV
Deputy Shotcrete 12/6/2022 No Access for Inspection PETER FOLLING
Footing/Foundation/Slab 5/25/2023 Not Ready for Inspection ROBERT PINA
Footing/Foundation/Slab 5/26/2023 Partial Approval ROBERT PINA
Reinforced Concrete Frame 6/5/2023 Partial Approval ROBERT PINA
Final 10/2/2023 Permit Finaled ROBERT PINA