4301 N VALLEY MEADOW ROAD 91436
Certificate Information: 4301 N VALLEY MEADOW ROAD 91436
- Application / Permit
- 21020-20000-01226
- Plan Check / Job No.
- B21VN07203
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW 10' HIGH X 190.75 LF RETAINING WALL AND 10' HIGH X 135 LF RETAINING WALL, 6 FT MAX ABOVE NATURAL GRADE IN THE REQUIRED SIDE YARD AND NEW SHORING FOR RETAINING WALL 190.75 LF , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/14/2023
Permit Application Status History
| Submitted | 6/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | RARES BODEA |
| Corrections Issued | 6/26/2021 | RARES BODEA |
| Quality Review Completed | 7/2/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| Applicant returned to address corrections | 11/1/2021 | RARES BODEA |
| Applicant returned to address corrections | 11/18/2021 | RARES BODEA |
| Plan Check Approved | 11/23/2021 | RARES BODEA |
| Issued | 4/13/2022 | APPLICANT |
| Permit Finaled-Status Void | 11/7/2023 | MICHAEL TEMPLE |
| Re-Activate Permit | 11/7/2023 | MICHAEL TEMPLE |
| Permit Finaled | 11/13/2023 | ROBERT PINA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2021 | CARLOS AGUILERA |
| Landscape for retaining wall | Cleared | 8/9/2021 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 11/23/2021 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2022 | Approved | DAVID SANDOVAL |
| Deputy Grading | 5/27/2022 | Approved | KIRK LINKLATER |
| Deputy Grading | 6/7/2022 | No Access for Inspection | VASIL MIHALEV |
| Deputy Other (see comments) | 6/8/2022 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 6/8/2022 | Approved | VASIL MIHALEV |
| Deputy Other (see comments) | 6/9/2022 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 6/13/2022 | Approved | KIRK LINKLATER |
| Masonry Wall/Backfill | 8/2/2022 | Approved | LANNY MERRICK |
| Masonry Wall/Backfill | 8/8/2022 | Partial Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 8/19/2022 | Partial Approval | MANUEL TEJADA |
| Deputy Shotcrete | 8/23/2022 | Approved | MANUEL TEJADA |
| Deputy Reinf. Concrete | 9/16/2022 | Approved | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 9/16/2022 | Partial Inspection | LANNY MERRICK |
| Deputy Reinf. Masonry | 10/3/2022 | Conditional Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 10/4/2022 | Approved | VASIL MIHALEV |
| Deputy Reinf. Masonry | 10/6/2022 | Conditional Approval | LANNY MERRICK |
| Masonry Wall/Backfill | 10/18/2022 | Partial Approval | MANUEL TEJADA |
| Piling/Pier/Caisson | 12/2/2022 | Partial Inspection | MANUEL TEJADA |
| Footing/Foundation/Slab | 6/13/2023 | Partial Approval | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 8/31/2023 | Not Ready for Inspection | BRIAN MILLER |
| Piling/Pier/Caisson | 8/31/2023 | Not Ready for Inspection | BRIAN MILLER |
| Final | 11/7/2023 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 11/13/2023 | Permit Finaled | ROBERT PINA |