3640 N MANDEVILLE CANYON ROAD 90049
Certificate Information: 3640 N MANDEVILLE CANYON ROAD 90049
- Application / Permit
- 21020-20000-01177
- Plan Check / Job No.
- B21VN06877
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALLS ON LOT 102.5 LINEAR FEET 10 FEET HIGH MAXIMUM W/SPLASH AND DIVERSION WALL PER LADBS GRADING DIVISION
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/25/2024
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | PETER MOSESIAN |
| Corrections Issued | 7/4/2021 | PETER MOSESIAN |
| Quality Review Completed | 7/16/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/31/2021 | APPLICANT |
| Applicant returned to address corrections | 2/23/2022 | PETER MOSESIAN |
| Plan Check Approved | 5/31/2022 | PETER MOSESIAN |
| Issued | 6/1/2022 | APPLICANT |
| Permit Finaled | 11/22/2024 | JOHNNY MIRANDA |
Permit Application Clearance Information
| ZA Case | Cleared | 10/5/2021 | LOUIS ORTEGA |
| Landscape for retaining wall | Cleared | 11/1/2021 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2022 | SAUL GARCIA |
| Watercourse | Cleared | 4/5/2022 | SAUL GARCIA |
Contact Information
| Architect | Tomalevski,, Vladimir Bogdanov; Lic. No.: C22417 | 8416 HAROLD WAY L&V TOMALEVSKI ARCHITECTS, INC. LOS ANGELES, CA 90069 |
| Contractor | Owner-Builder | , |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Markov,, George P; Lic. No.: C55855 | 1623 THOMPSON AVE GLENDALE, CA 91201 |
| Engineer | Ostowari,, Sohrab; Lic. No.: C41014 | 7012 HELMSDALE RD WEST HILLS, CA 91307 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/3/2022 | Approved | CHARLES POWELL |
| Piling/Pier/Caisson | 9/8/2022 | Partial Inspection | TIMOTHY POWELL |
| Deputy Reinf. Concrete | 9/9/2022 | Partial Approval | MICHAEL TEMPLE |
| Deputy Reinf. Concrete | 9/12/2022 | Approved | TIMOTHY POWELL |
| Piling/Pier/Caisson | 9/12/2022 | Partial Approval | TIMOTHY POWELL |
| Special/Order Compliance | 10/6/2022 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 10/25/2022 | Corrections Issued | CHARLES POWELL |
| Footing/Foundation/Slab | 10/25/2022 | Not Ready for Inspection | CHARLES POWELL |
| Footing/Foundation/Slab | 10/26/2022 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Corrections Issued | CHARLES POWELL |
| Footing/Foundation/Slab | 2/8/2023 | Corrections Issued | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 8/15/2023 | Partial Approval | CHARLES POWELL |
| Masonry Wall/Backfill | 10/5/2023 | Partial Approval | CHARLES POWELL |
| Final | 3/26/2024 | Corrections Issued | JOHNNY MIRANDA |
| Final | 11/22/2024 | Permit Finaled | JOHNNY MIRANDA |