7366 S OSAGE AVE 90045
Certificate Information: 7366 S OSAGE AVE 90045
- Application / Permit
- 21020-20000-00509
- Plan Check / Job No.
- B21VN03020
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- SHORING FOR NEW THREE STORY STORAGE BUILDING OVER THREE STORY STORAGE 200 LINEAR FT LONG AT NORTH AND SOUTH PORTION OF THE SITE AND 150 LF LONG AT EAST AND WEST PORTION OF THE SITE , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | RARES BODEA |
| Corrections Issued | 4/10/2021 | RARES BODEA |
| Quality Review Completed | 4/15/2021 | STEVEN KIM |
| Applicant returned to address corrections | 5/14/2021 | RARES BODEA |
| Applicant returned to address corrections | 7/12/2021 | RARES BODEA |
| Plan Check Approved | 4/20/2022 | RARES BODEA |
| Issued | 4/21/2022 | APPLICANT |
| Permit Finaled | 1/15/2025 | DERRICK SPENCER |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 2/28/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 3/1/2022 | PEDRO AYALA |
| Miscellaneous | Cleared | 3/7/2022 | KENTON TRINH |
| ZA Case | Cleared | 3/7/2022 | KENTON TRINH |
| Grading Pre-Inspection | Cleared | 3/22/2022 | PATRICK MISCHLICH |
Contact Information
| Contractor | Near-Cal Corp; Lic. No.: 230077-B | 512 CHANEY STREET LAKE ELSINORE, CA 92530 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough | 5/26/2022 | Partial Inspection | GRANT WOODS |
| Rough | 6/6/2022 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/13/2022 | Partial Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 6/22/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/23/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/24/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/27/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/28/2022 | Approved | DERRICK SPENCER |
| Rough | 7/5/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 7/18/2022 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/24/2022 | Partial Approval | DERRICK SPENCER |
| Deputy Grading | 1/27/2023 | Approved | DERRICK SPENCER |
| Deputy Grading | 1/30/2023 | Approved | DERRICK SPENCER |
| Final | 6/12/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 6/17/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 6/24/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 1/15/2025 | Permit Finaled | DERRICK SPENCER |