7366 S OSAGE AVE 90045

Certificate Information: 7366 S OSAGE AVE 90045

Application / Permit
21020-20000-00509
Plan Check / Job No.
B21VN03020
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Shoring (Temporary)
Work Description
SHORING FOR NEW THREE STORY STORAGE BUILDING OVER THREE STORY STORAGE 200 LINEAR FT LONG AT NORTH AND SOUTH PORTION OF THE SITE AND 150 LF LONG AT EAST AND WEST PORTION OF THE SITE , ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/21/2022
Issuing Office
Current Status
Permit Finaled on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 RARES BODEA
Corrections Issued 4/10/2021 RARES BODEA
Quality Review Completed 4/15/2021 STEVEN KIM
Applicant returned to address corrections 5/14/2021 RARES BODEA
Applicant returned to address corrections 7/12/2021 RARES BODEA
Plan Check Approved 4/20/2022 RARES BODEA
Issued 4/21/2022 APPLICANT
Permit Finaled 1/15/2025 DERRICK SPENCER

Permit Application Clearance Information

Work Adjacent to Public Way Cleared 2/28/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 3/1/2022 SAUL GARCIA
Specific Plan Cleared 3/1/2022 PEDRO AYALA
Miscellaneous Cleared 3/7/2022 KENTON TRINH
ZA Case Cleared 3/7/2022 KENTON TRINH
Grading Pre-Inspection Cleared 3/22/2022 PATRICK MISCHLICH

Contact Information

Contractor Near-Cal Corp; Lic. No.: 230077-B 512 CHANEY STREET      LAKE ELSINORE, CA 92530
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

DERRICK SPENCER, (310) 914-3919 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough 5/26/2022 Partial Inspection GRANT WOODS
Rough 6/6/2022 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 6/13/2022 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 6/22/2022 Approved DERRICK SPENCER
Deputy Steel/Welding 6/23/2022 Approved DERRICK SPENCER
Deputy Steel/Welding 6/24/2022 Approved DERRICK SPENCER
Deputy Steel/Welding 6/27/2022 Approved DERRICK SPENCER
Deputy Steel/Welding 6/28/2022 Approved DERRICK SPENCER
Rough 7/5/2022 Approved DERRICK SPENCER
Deputy Steel/Welding 7/18/2022 Approved DERRICK SPENCER
Footing/Foundation/Slab 8/24/2022 Partial Approval DERRICK SPENCER
Deputy Grading 1/27/2023 Approved DERRICK SPENCER
Deputy Grading 1/30/2023 Approved DERRICK SPENCER
Final 6/12/2024 Not Ready for Inspection DERRICK SPENCER
Final 6/17/2024 Not Ready for Inspection DERRICK SPENCER
Final 6/24/2024 Not Ready for Inspection DERRICK SPENCER
Final 1/15/2025 Permit Finaled DERRICK SPENCER