4952 N VANALDEN AVE 91356
Certificate Information: 4952 N VANALDEN AVE 91356
- Application / Permit
- 21020-20000-00350
- Plan Check / Job No.
- B21VN02242
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALL. (L = 170'-9" FT.; H = 10 FT.)
- Permit Issued
- Issued on 8/15/2022
- Issuing Office
- Valley
- Current Status
- Issued on 8/15/2022
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | COLIN LOREDO |
| Corrections Issued | 3/25/2021 | COLIN LOREDO |
| Quality Review Completed | 4/13/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/24/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 8/16/2021 | COLIN LOREDO |
| Plan Check Approved | 7/28/2022 | COLIN LOREDO |
| Issued | 8/15/2022 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 7/28/2022 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 7/28/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/5/2023 | Partial Approval | ROBERT PINA |
| Piling/Pier/Caisson | 7/5/2023 | Partial Approval | ROBERT PINA |
| Deputy Reinf. Concrete | 7/10/2023 | Approved | ROBERT PINA |
| Deputy Reinf. Concrete | 8/9/2023 | Approved | ALEXANDER HELFER |
| Footing/Foundation/Slab | 8/10/2023 | Partial Approval | ROBERT PINA |
| Piling/Pier/Caisson | 8/10/2023 | Partial Approval | ROBERT PINA |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Approved | ROBERT PINA |
| Deputy Shotcrete | 9/1/2023 | Approved | BRIAN MILLER |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Partial Approval | ROBERT PINA |
| Footing/Foundation/Slab | 9/26/2023 | Partial Approval | ROBERT PINA |
| Piling/Pier/Caisson | 10/24/2023 | Approved | ROBERT PINA |
| Final | 1/22/2024 | Corrections Issued | ROBERT PINA |
| Deputy Reinf. Concrete | 3/4/2024 | Approved | ROBERT PINA |