18102 W GUILDFORD LANE 91326
Certificate Information: 18102 W GUILDFORD LANE 91326
- Application / Permit
- 21020-20000-00190
- Plan Check / Job No.
- B21VN01284
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- 2 NEW RETAINING WALLS (RET. WALL 1: L=25' H= 7'; RET. WALL 2: L= 145', H= 8')
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Current Status
- Issued on 2/17/2022
Permit Application Status History
| Submitted | 2/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | SEAN SHAHMIRI |
| Corrections Issued | 3/10/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 3/11/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 3/12/2021 | APPLICANT |
| Applicant returned to address corrections | 6/24/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 10/21/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 12/13/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 2/10/2022 | SEAN SHAHMIRI |
| Issued | 2/17/2022 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/23/2021 | SEAN SHAHMIRI |
| Landscape for retaining wall | Cleared | 2/8/2022 | LAUREN PADICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirosian,, Hayk Sam; Lic. No.: C52563 | 537 NOLAN AVE GLENDALE, CA 91202 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 3/1/2022 | Corrections Issued | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 3/9/2022 | Partial Approval | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 3/16/2022 | Partial Approval | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Partial Approval | MANUEL TEJADA |
| Reinforced Concrete Frame | 3/22/2022 | Not Ready for Inspection | MANUEL TEJADA |
| Deputy Reinf. Concrete | 3/23/2022 | Approved | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 5/5/2022 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 5/10/2022 | Corrections Issued | BRIAN MILLER |
| Excavation/Setback/Form/Re-Bar | 5/12/2022 | Partial Inspection | BRIAN MILLER |
| Excavation/Setback/Form/Re-Bar | 5/24/2022 | Partial Approval | BRIAN MILLER |
| Masonry Wall/Backfill | 6/2/2022 | Conditional Approval | BRIAN MILLER |
| Final | 6/23/2022 | Not Ready for Inspection | BRIAN MILLER |