13956 W AUBREY ROAD 90210
Certificate Information: 13956 W AUBREY ROAD 90210
- Application / Permit
- 21020-10002-02417
- Plan Check / Job No.
- B24LA10828
- Group
- Building
- Type
- Nonbldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- Supplemental to Permit 21020-10000-02417 for minor structural revisions in retaining wall foundation design.
- Permit Issued
- Issued on 6/17/2024
- Issuing Office
- Current Status
- Issued on 6/17/2024
Permit Application Status History
| Submitted | 6/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2024 | CHUNG-WEN CHUANG |
| Plan Check Approved | 6/14/2024 | CHUNG-WEN CHUANG |
| Issued | 6/17/2024 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Reis Ey Inc; Lic. No.: 1067133-B | , |
| Engineer | Labib,, Youhanna T.; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 6/18/2024 | Partial Approval | MANUEL TEJADA |
| Piling/Pier/Caisson | 6/21/2024 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 6/26/2024 | Partial Approval | MANUEL TEJADA |
| Piling/Pier/Caisson | 6/26/2024 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 7/5/2024 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 7/25/2024 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 7/26/2024 | Not Ready for Inspection | MANUEL TEJADA |
| Footing/Foundation/Slab | 8/9/2024 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 8/19/2024 | Partial Approval | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 8/20/2024 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 8/20/2024 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 8/23/2024 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 8/27/2024 | Partial Inspection | MANUEL TEJADA |
| Footing/Foundation/Slab | 9/10/2024 | Not Ready for Inspection | MANUEL TEJADA |
| Footing/Foundation/Slab | 10/8/2024 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 12/20/2024 | Partial Approval | MANUEL TEJADA |