2217 S DUXBURY CIR 90034
Certificate Information: 2217 S DUXBURY CIR 90034
- Application / Permit
- 21020-10001-00913
- Plan Check / Job No.
- B22LA21785
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- (n) TRELLIS 2 of 2
- Permit Issued
- Issued on 2/1/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | KELVIN CHUONG |
| Corrections Issued | 11/8/2022 | KELVIN CHUONG |
| Quality Review Completed | 11/10/2022 | KEN GILL |
| Building Plans Picked Up | 11/14/2022 | APPLICANT |
| Plan Check Approved | 1/31/2023 | KELVIN CHUONG |
| Issued | 2/1/2023 | APPLICANT |
| CofO in Progress | 9/30/2025 | ASHLEY THOMPSON |
| Permit Finaled | 11/13/2025 | RICHARD STEINBACH |
| CofO Issued | 11/13/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/13/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Concord Construction Inc; Lic. No.: 1077056-B | 449 SOUTH BEVERLY DRIVE 1ST FLOOR BEVERLY HILLS, CA 90212 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 3/21/2023 | No Access for Inspection | ASHLEY THOMPSON |
| Deputy Steel/Welding | 5/26/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 10/24/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 3/5/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/11/2025 | Approved | ASHLEY THOMPSON |
| Final | 7/11/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 7/11/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Barrier | 7/11/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Final | 7/11/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 7/11/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 7/11/2025 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 7/11/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 7/11/2025 | Approved | ASHLEY THOMPSON |
| Final | 9/3/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Service/Power Release | 9/3/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 9/12/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Service/Power Release | 9/12/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 9/25/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Service/Power Release | 9/25/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 10/1/2025 | OK to Issue CofO | ASHLEY THOMPSON |
| Service/Power Release | 10/1/2025 | Approved | ASHLEY THOMPSON |