717 N SEWARD ST 90038

Certificate Information: 717 N SEWARD ST 90038

Application / Permit
21020-10000-02827
Plan Check / Job No.
B21LA23540
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Shoring (Temporary)
Work Description
TEMPORARY SHORING WITH LAGGING & SOLDIER PILES FOR NEW 5 STORY TYPE I-B OFFICE BUILDING OVER 2 LEVELS SUBTERRANEAN PARKING GARAGE (BUILDING APPLICATION # 21010-10000-05063)
Permit Issued
Issued on 11/21/2023
Issuing Office
Current Status
Permit Finaled on 4/16/2026

Permit Application Status History

Submitted 12/17/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 GARO TELMI
Corrections Issued 1/28/2022 GARO TELMI
Quality Review Completed 2/2/2022 KEN GILL
Building Plans Picked Up 2/4/2022 APPLICANT
Applicant returned to address corrections 4/21/2022 GARO TELMI
Applicant returned to address corrections 9/15/2023 GARO TELMI
Applicant returned to address corrections 11/15/2023 GARO TELMI
Plan Check Approved 11/21/2023 GARO TELMI
Issued 11/21/2023 APPLICANT
Permit Finaled 4/15/2026 MARTIN TAVITIAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/24/2022 WALLIE JONG
Encroachment in public way Cleared 12/13/2022 JEREMY CHOK
Excavation more than 5-ft deep Cleared 3/23/2023 CALOSHA APPROVED
ZA Case Cleared 6/15/2023 DANIEL CORONADO
ZI Cleared 6/15/2023 DANIEL CORONADO
CPC Cleared 7/27/2023 DANIEL CORONADO
Work Adjacent to Public Way Cleared 10/23/2023 JOSE RODRIGUEZ
Construction near power lines Cleared 11/4/2023 RIDWAN HARDY
Construction within easement Cleared 11/4/2023 RIDWAN HARDY

Contact Information

Contractor Kprs Construction Services Inc; Lic. No.: 751130-B 2850 SATURN STREET      BREA, CA 92821
Engineer Cefali,, David Allen; Lic. No.: S3658 4344 LAUREL CANYON BLVD_STE 3      STUDIO CITY, CA 91604
Engineer Davis,, Richard Hays; Lic. No.: C48082 2015 CANTATA DR      LOS ANGELES, CA 90068
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 11/27/2023 Partial Inspection GREGORY POMISH
Piling/Pier/Caisson 11/27/2023 Partial Inspection GREGORY POMISH
Pre-Inspection 11/27/2023 Partial Approval GREGORY POMISH
Deputy Grading 12/5/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/5/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/6/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/6/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/19/2023 No Access for Inspection MICHAEL ROSENBERG
Deputy Grading 12/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 1/4/2024 Conditional Approval RICARDO ROBLES
Deputy Grading 1/10/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 1/18/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 1/24/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 1/25/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 1/26/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 1/29/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 1/30/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 1/31/2024 Partial Approval EDWIN GREGORYONA
Piling/Pier/Caisson 1/31/2024 Partial Inspection EDWIN GREGORYONA
Deputy Grading 2/1/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 2/12/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 2/13/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 2/14/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 2/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 2/21/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 2/27/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 2/29/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 3/8/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 3/13/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 3/14/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 3/18/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 3/20/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 3/21/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/30/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/28/2024 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 7/16/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/17/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/23/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/25/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/26/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/6/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/7/2024 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 8/8/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/9/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 8/14/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/15/2024 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 8/15/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/16/2024 Approved TIMOTHY POWELL
Deputy Reinf. Concrete 8/16/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/26/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/29/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/3/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/4/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/11/2024 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 9/12/2024 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 9/12/2024 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 9/16/2024 Partial Approval MARTIN TAVITIAN
Deputy Reinf. Concrete 9/30/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/8/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/10/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/15/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 10/22/2024 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 10/30/2024 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 10/31/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 11/5/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/12/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/13/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/21/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/2/2024 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 12/3/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/6/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/11/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 12/12/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/16/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 12/20/2024 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 12/20/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/20/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 12/31/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/31/2024 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 12/31/2024 Partial Approval EDWIN GREGORYONA
Deputy Grading 1/6/2025 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/6/2025 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 1/6/2025 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/21/2025 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/23/2025 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/29/2025 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/20/2025 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 2/20/2025 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/11/2025 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 3/11/2025 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/13/2025 Partial Approval EDWIN GREGORYONA
Final 4/15/2026 Permit Finaled MARTIN TAVITIAN