717 N SEWARD ST 90038
Certificate Information: 717 N SEWARD ST 90038
- Application / Permit
- 21020-10000-02827
- Plan Check / Job No.
- B21LA23540
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- TEMPORARY SHORING WITH LAGGING & SOLDIER PILES FOR NEW 5 STORY TYPE I-B OFFICE BUILDING OVER 2 LEVELS SUBTERRANEAN PARKING GARAGE (BUILDING APPLICATION # 21010-10000-05063)
- Permit Issued
- Issued on 11/21/2023
- Issuing Office
- Current Status
- Permit Finaled on 4/16/2026
Permit Application Status History
| Submitted | 12/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | GARO TELMI |
| Corrections Issued | 1/28/2022 | GARO TELMI |
| Quality Review Completed | 2/2/2022 | KEN GILL |
| Building Plans Picked Up | 2/4/2022 | APPLICANT |
| Applicant returned to address corrections | 4/21/2022 | GARO TELMI |
| Applicant returned to address corrections | 9/15/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/15/2023 | GARO TELMI |
| Plan Check Approved | 11/21/2023 | GARO TELMI |
| Issued | 11/21/2023 | APPLICANT |
| Permit Finaled | 4/15/2026 | MARTIN TAVITIAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2022 | WALLIE JONG |
| Encroachment in public way | Cleared | 12/13/2022 | JEREMY CHOK |
| Excavation more than 5-ft deep | Cleared | 3/23/2023 | CALOSHA APPROVED |
| ZA Case | Cleared | 6/15/2023 | DANIEL CORONADO |
| ZI | Cleared | 6/15/2023 | DANIEL CORONADO |
| CPC | Cleared | 7/27/2023 | DANIEL CORONADO |
| Work Adjacent to Public Way | Cleared | 10/23/2023 | JOSE RODRIGUEZ |
| Construction near power lines | Cleared | 11/4/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/4/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Kprs Construction Services Inc; Lic. No.: 751130-B | 2850 SATURN STREET BREA, CA 92821 |
| Engineer | Cefali,, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
| Engineer | Davis,, Richard Hays; Lic. No.: C48082 | 2015 CANTATA DR LOS ANGELES, CA 90068 |
| Engineer | Derkalousdian,, Hrair Harry; Lic. No.: C79694 | 3622 VIRGINIA STREET GLENDALE, CA 91214 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 11/27/2023 | Partial Inspection | GREGORY POMISH |
| Piling/Pier/Caisson | 11/27/2023 | Partial Inspection | GREGORY POMISH |
| Pre-Inspection | 11/27/2023 | Partial Approval | GREGORY POMISH |
| Deputy Grading | 12/5/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 12/5/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 12/6/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 12/6/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 12/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 12/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 12/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 12/19/2023 | No Access for Inspection | MICHAEL ROSENBERG |
| Deputy Grading | 12/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 1/4/2024 | Conditional Approval | RICARDO ROBLES |
| Deputy Grading | 1/10/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Other (see comments) | 1/18/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 1/24/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 1/25/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 1/26/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 1/29/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 1/30/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 1/31/2024 | Partial Approval | EDWIN GREGORYONA |
| Piling/Pier/Caisson | 1/31/2024 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Grading | 2/1/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/12/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/13/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/14/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/15/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/21/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/27/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 2/29/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 3/8/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/13/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/14/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/18/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 3/20/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 3/21/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/30/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 6/28/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 7/16/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 7/17/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 7/23/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 7/25/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 7/26/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/6/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/7/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 8/8/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/9/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Shotcrete | 8/14/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/15/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 8/15/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/16/2024 | Approved | TIMOTHY POWELL |
| Deputy Reinf. Concrete | 8/16/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/26/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/29/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 9/3/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 9/4/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 9/11/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 9/12/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 9/12/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 9/16/2024 | Partial Approval | MARTIN TAVITIAN |
| Deputy Reinf. Concrete | 9/30/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/8/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/10/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/15/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 10/22/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Other (see comments) | 10/30/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Other (see comments) | 10/31/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 11/5/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 11/12/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 11/13/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 11/21/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 12/2/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 12/3/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 12/6/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 12/11/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 12/12/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 12/16/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 12/20/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Other (see comments) | 12/20/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 12/20/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 12/31/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 12/31/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 12/31/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 1/6/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 1/6/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 1/6/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 1/21/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 1/23/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 1/29/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 2/20/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 2/20/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 3/11/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 3/11/2025 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 6/13/2025 | Partial Approval | EDWIN GREGORYONA |
| Final | 4/15/2026 | Permit Finaled | MARTIN TAVITIAN |