865 N NAPOLI DR 90272
Certificate Information: 865 N NAPOLI DR 90272
- Application / Permit
- 21020-10000-02685
- Plan Check / Job No.
- B21LA22279
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALLS 3 OF 5
- Permit Issued
- Issued on 7/8/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/27/2025
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | ZAW HAN |
| Corrections Issued | 12/21/2021 | ZAW HAN |
| Quality Review Completed | 12/22/2021 | KEN GILL |
| Applicant returned to address corrections | 3/8/2022 | ZAW HAN |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Applicant returned to address corrections | 4/14/2022 | ZAW HAN |
| Applicant returned to address corrections | 6/22/2022 | ZAW HAN |
| Applicant returned to address corrections | 6/27/2022 | ZAW HAN |
| Applicant returned to address corrections | 6/29/2022 | ZAW HAN |
| Plan Check Approved | 7/7/2022 | ZAW HAN |
| Issued | 7/8/2022 | APPLICANT |
| Permit Finaled | 1/24/2025 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 1/25/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 1/25/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 1/25/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 1/25/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 1/25/2022 | ANTHONY MAINEZ |
| Permit | Cleared | 1/25/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 1/25/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | ANTHONY MAINEZ |
| Frnt yard landscape/Water mgmt | Cleared | 3/2/2022 | MAXFIELD VERMY |
| Landscape for retaining wall | Cleared | 3/2/2022 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 3/11/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 4/25/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/25/2022 | ANTHONY MAINEZ |
| Disturb/Remove Protected Trees | Cleared | 6/1/2022 | ADALBERTO VERA |
| Trees in Parkway | Cleared | 6/1/2022 | ADALBERTO VERA |
| Building over 36-ft | Cleared | 6/29/2022 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 6/29/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 6/29/2022 | KIRK LINKLATER |
| Grading Pre-Inspection | Cleared | 6/29/2022 | KIRK LINKLATER |
| Green Code | Cleared | 6/29/2022 | ZAW HAN |
| Haul Route | Cleared | 6/29/2022 | VERONICA LOPEZ |
Contact Information
| Contractor | Gibson Gordon Construction; Lic. No.: 524012-B | 3000 31ST STREET SUITE G SANTA MONICA, CA 90405 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: C40985 | 30423 CANWOOD ST STE 223 AGOURA HILLS, CA 91301 |
| Engineer | Schmahl,, Lawrence Joseph; Lic. No.: L5748 | 11209 HOWARD STREET WHITTIER, CA 90606 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/3/2022 | Partial Approval | JONATHAN HOM |
| Rough | 8/3/2022 | Partial Inspection | JONATHAN HOM |
| Rough | 8/5/2022 | Partial Approval | TIMOTHY POWELL |
| Piling/Pier/Caisson | 9/1/2022 | Partial Approval | TIMOTHY POWELL |
| Piling/Pier/Caisson | 9/8/2022 | Partial Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 9/15/2022 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 9/15/2022 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 9/19/2022 | Partial Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 5/25/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 6/8/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Footing/Foundation/Slab | 1/18/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Final | 1/24/2025 | Permit Finaled | JOHNNY MIRANDA |