3045 S CRENSHAW BLVD 90016
Certificate Information: 3045 S CRENSHAW BLVD 90016
- Application / Permit
- 21020-10000-02646
- Plan Check / Job No.
- B21LA21841
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- SHORING FOR NEW MIXED USE APARTMENT BUILDING.
- Permit Issued
- Issued on 4/20/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/19/2025
- Certificate of Occupancy
- CofO Corrected More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | KEVIN MORALES |
| Corrections Issued | 12/22/2021 | KEVIN MORALES |
| Quality Review Completed | 1/4/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 1/6/2022 | APPLICANT |
| Applicant returned to address corrections | 10/21/2022 | KEVIN MORALES |
| Plan Check Approved | 4/19/2023 | KEVIN MORALES |
| Issued | 4/20/2023 | APPLICANT |
| Permit Finaled-Status Void | 10/29/2025 | JAMES POWERS |
| Re-Activate Permit | 12/19/2025 | JAMES POWERS |
| Permit Finaled | 12/19/2025 | JAMES POWERS |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 6/23/2022 | CALOSHA APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2022 | CHRISTOPHER ROCHA |
| Work Adjacent to Public Way | Cleared | 4/5/2023 | JOSE RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 6/20/2023 | Partial Inspection | GREGORY POMISH |
| Deputy Grading | 6/21/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 6/21/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 6/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 8/16/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 8/24/2023 | No Access for Inspection | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 10/25/2023 | Conditional Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 10/26/2023 | Conditional Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 10/31/2023 | Conditional Approval | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 12/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Final | 10/29/2025 | Not Ready for Inspection | JAMES POWERS |